Hi Everyone,
It's time for me to have my own thread and share our experiences with building process.
We started our KDR journey back in April 2014.
After sifting through many project homes... we selected three project homes builder....Rawson , Coral and our favorite Sekisui.
After adding and changing floor plan of Rawson... we comes to conclusion it's does not suit for us.
Therefore the remaining two builders were Coral and sekisui.
1. Coral - Miami 40
2. Sekisui - Aron 395
In order to finalize our decision we went heads on with both builders... paid 2k each to both builder to start up NHP.
This process started from April 2014 to Nov 2014.
The final decision was made on " The Outdoor Living Area". This outdoor living area was able to fit into our current land size, with Sekisui house plan. So we signed our contract end of Nov 2014 with Sekisui.
Sekisui submitted DA approval to our local council back in March 2015.
our local council gives us deferred approval with conditions back in Aug 2015, due to easement.
Which I simply label as " THE EASEMENT SAGA". (will talk about it later)
The good news is just very recently we have final DA approval.... two days ago.
Now we have to get CC and booked in for demolition - 7 of March.
Likes to thanks in advance for those who has helped with many of my questions in the past and for future.
_________________________________________________________________________
Timing of DA approval :
Main house: DA (a)
Stormwater connection to neighbour house: DA ( b)
03.03.2015 DA (a) submitted by Sekisui to council
17.08.2015 DA (a) Deferred approval issued by council
10.10.2015 DA (b) submitted as part of DA (a) schedule requirement
15.12.2015 DA (b) Approved by council
23 12.2015 CC applied for DA (b)
20.01.2016 DA (a) activated by council - all DA (a) requirement fulfilled
19.02.2016 DA (a) Construction Certificate issued by Private Certifier
18.03.2016 DA (b) first response from council asked for more info of CC for DA (b)
22.03.2016 Demolish home
21.04.2016 DA (b) New stormwater design and calculations submitted to council
26.05.2016 Council instructing to submit section 96 modification for both DA
07.06.2016 DA (a) submit storm water modification (new rainwater tank design)
10.06.2016 DA (b) submit storm water modification - reflecting DA (a) Modification
12.09.2016 MOD on DA (b) approved by council
27.09.2016 MOD on DA (a) approved by council
17.10.2016 CC on DA (b) approved
27.10.2016 All Clear received from Burbank
Build Timing :
06.12.2016 Fence by Burbank
12.12.2016 Tigertails
14.12.2016 Cut and fill
09.01.2017 Siltation fence extension
11.01.2017 Piering
18.01.2017 Under slab plumbing
19.01.2017 Materials delivered for concrete slab
20.01.2017 working on waffle pods for concrete slab