We are building a Parkhill 36 by Clarendon Homes in Coomera Retreat on the Gold Coast.
Some of you may have read earlier that we placed a deposit with a different builder. Well after months of arguing with them over trivial details that they wanted to charge me a fortune for (they LOVE putting retaining walls on to blocks that are essentially FLAT!!), I have given up and gone with Clarendon.
We have selected the Parkhill 36 with a few modifications.
We chose this home for a number of reasons but the two major factors were.. It felt like "Home" when we walked through the display. Many other just didn't do that for us. And secondly, it was by far the easiest to modify and add the second master bedroom to and still have plenty of living area.
You might like to also check out our blog which has more detailed info Our Build Blog
Cheers
Paul
THE JOURNEY
FROM THE BEGINNING
03/01/2015 - Paid deposit and signed contract for block of land in Coomera Retreat.
09/01/2015 - Land given unconditional approval by bank. Looks like we own a patch of dirt haha!!
10/01/2015 - Paid deposit to "First Builder" and took pics of our land!! Click Here For Pictures
16/01/2015 - Joined Homeone Forum. A important milestone I think haha
18/01/2015 - Back to see sales rep and removed the Alfresco and converted back to internal living space.
09/02/2015 - First tender and plan presentation. WOW.. The $$$$ really start adding up. If you wish to sneeze in that corner.. that will cost you a extra $1500.00 lol
20/02/2015 - Second Tender and revised plans received after me complaining to customer liaison about time taken for simple amendments. (And yes.. I come from a building background so have some knowledge of time frames)
21/03/2015 - Paid deposit to Clarendon Homes. Bigger home, higher costs, but already much happier with results achieved in a quick 3 weeks of talking with them.
21/03/2015 - Posted image of floor plan and front elevation. Will post our modified version when we get it
01/06/2015 - Unconditional Approval for finance from RAMS
12/06/2015 - Colour Selections at Clarendon Studio Click here for pictures
16/06/2015 - Settlement of land. We now own a block of dirt!!!
08/07/2015 - Received Building Works Approval from private certifier.
11/08/2015 - Received Authority to Commence Letter from Rams
11/09/2015 - Final Plans.. FINALLY!! Click Here For Pictures
CONSTRUCTION 2015
29/09/2015 - Site Scrape Click Here For Pictures
01/10/2015 - Gravel delivered for driveway and house pegged out. Click Here For Pictures
06/10/2015 - Garage Beam and Peering Click Here For Pictures
07/10/2015 - Trenching, Plumbing and Meterbox Click Here For Pictures
08/10/2015 - Mesh and Rio delivered to site. Click Here For Pictures
10/10/2015 - Slab boxed up, pods and mesh installed. Click Here For Pictures
12/10/2015 - SLAB POURED!!! Click Here For Pictures
13/10/2015 - Dirt from site scrape and trenches spread back around yard to slope away from slab.
14/10/2015 - Waterproofing fitted to outside edges of slab
15/10/2015 - Steel beams delivered to site
21/10/2015 - Lower floor framing erected. Click Here For Pictures
22/10/2015 - Temp Bracing, Bracing Ply, Floor Joists and Safety Rails installed.Click Here For Pictures
23/10/2015 - Second Floor going up. Click Here For Pictures
24/10/2015 - Upper floor frames completed, lower floor roof done and part of upper floor roof completed. Click Here For Pictures
30/10/2015 - Fascia and Gutter fitted to upper floor roof. Click Here For Pictures
02/11/2015 - Insulation for roof delivered.
03/11/2015 - Upper floor roof installed. Click Here For Pictures
06/11/2015 - Plumbing installed. Click Here For Pictures
14/11/2015 - Fascia & Gutter installed to lower roof sections. Safety rails fitted for roof plumbers. Click Here For Pictures
19/11/2015 - Lower Roof fitted Click Here For Pictures
21/11/2015 - Safety Rails installed over Garage Roof Click Here For Pictures
21/11/2015 - Electrical Rough In Done. Click Here For Pictures
24/11/2015 - Some of our windows have been delivered and more electrical work completed! Click Here For Pictures
26/11/2015 - Windows installed and some of the data cables ran. Click Here For Pictures
02/12/2015 - Bricks and Front Door delivered Click Here For Pictures
03/12/2015 - More bricks and brickies sand delivered... Click Here For Pictures
04/12/2015 - Front Door fitted, Brickies on site!!! Click Here For Pictures
08/12/2015 - More Brick Progress and some pics of the Amazing Cabling lol Click Here For Pictures
10/12/2015 - And More Bricks!!!! Click Here For Pictures
14/12/2015 - Scaffolding erected for brickies to continue Click Here For Pictures
14/12/2015 - Some rectifications completed... Click Here For Pictures
15/12/2015 - Insulation fitted Click Here For Pictures
18/12/2015 - Plasterboard Hung Click Here For Pictures
21/12/2015 - Brickwork Completed!! Click Here For Pictures
CONSTRUCTION 2016
04/01/2016 - Plasterers returned to do joints Click Here For Pictures
05/01/2016 - Front bricks rendered!! Click Here For Pictures
06/01/2016 - Front yard cleaned up Click Here For Pictures
08/01/2016 - Cornice Fitted Click Here For Pictures
12/01/2016 - Soffit and external cladding started Click Here For Pictures
12/01/2016 - Cladding Update Click Here For Pictures
13/01/2016 - Upper Floor Cladding Completed Click Here For Pictures
21/01/2016 - Soffits and Cladding are completed, Downpipes fitted to upper level and now painting to the upper floor has started. Click Here For Pictures
22/01/2016 - Bricks have been cleaned down. Click Here For Pictures
25/01/2016 - Stairs Fitted!! Click Here For Pictures
01/02/2016 - Wet Areas Waterproofed Click Here For Pictures
02/02/2016 - Fit Out started and Electrical Click Here For Pictures
10/02/2016 - Cabinets Going In Click Here For Pictures
15/02/2016 - Tiles Started Click Here For Pictures
21/02/2016 - Tiles Update Click Here For Pictures
23/02/2016 - More Tiles Updates and Benchtops Fitted Click Here For Pictures
28/02/2016 - Prep work started for painting Click Here For Pictures
02/03/2016 - Ceilings painted, Doors primed and first coat done on walls. We have a Garage Door!! Click Here For Pictures
19-03-2016 - Temp fencing removed, Shower screens going in, Electrical fit out started!!! Click Here For Pictures
31-03-2016 - Done walk through with supervisor and listed all defects that need to be repaired / replaced.
12-04-2016 - Hand Over!! Click Here For Pictures