Hey all, I have been lurking around here for awhile now watching everyone's build threads. I thought it about time I created my own. Still kind of figuring out how this site works so please forgive me if I get things a bit wrong Our journey so far (as well as I can remember anyhow) has been:
26/6 - our first contact with Stylemaster
13/07/2017 - Contract for land purchase signed
5/8 - Initial deposit paid to Stylemaster to get ball rolling with soil tests etc
4/12 - Land settled
8/12 Contract with Stylemaster signed
9/01 - Tile selection
18/01 - colour selection
12/02 - Authority to commence issued from lender
We are now at the stage where we are waiting for things to happen. We got a phone call from our site supervisor advising that our site cut should be happening on the 5th of March. I am very excited to see this happen as then maybe I will feel like it is actually happening. Feels like it has taken forever to get here due to issues along the way. Hopefully the build process isn't too painful.
I will add in house plans and colour selections etc in following posts.