Browse Forums Building A New House Re: Sezza's Build SOR Perth. waiting.. waiting... 341Feb 18, 2011 5:49 pm Built with Sw1tch H0mes >Build thread< House status 15/12: Gates and A/C finally installed! Sep 09 Bought block, Dec 09 Engaged builder, Jul '11 Moved in Re: Sezza's Build SOR Perth. waiting.. waiting... 342Feb 18, 2011 7:52 pm Preliminary agreement 23/11 Contract 22/03 Prestart 06/04 - finalised on 30/04 Unconditional approval 10/05 Demolition 05/07 Slab 26/08 Brickwork 13/09-06/10 Roof frame started 07/10 viewtopic.php?f=31&t=32292 Re: Sezza's Build SOR Perth. waiting.. waiting... 343Feb 19, 2011 2:41 am SEZZA'S BANKSIA DESIGNER viewtopic.php?f=31&t=33423 Building with SPH SOR - Baldivis. 3/5/10 Prestart 30/5/10 Final Plans Arrive 18/8/10 Siteworks 26/8/10 Slab 14/9/10-14/10/10 Bricks (2 Man Team) 25/10/10 Roof Frame and Roof Tiles 15/11/10 Rendering -Inside walls and Front of House Lock up and Locked Out!!! 10/12[/size] Re: Sezza's Build 344Feb 21, 2011 11:15 pm SEZZA'S BANKSIA DESIGNER viewtopic.php?f=31&t=33423 Building with SPH SOR - Baldivis. 3/5/10 Prestart 30/5/10 Final Plans Arrive 18/8/10 Siteworks 26/8/10 Slab 14/9/10-14/10/10 Bricks (2 Man Team) 25/10/10 Roof Frame and Roof Tiles 15/11/10 Rendering -Inside walls and Front of House Lock up and Locked Out!!! 10/12[/size] Re: Sezza's Perth Build 345Feb 22, 2011 11:31 am my new build thread- Ben Trager https://forum.homeone.com.au/viewtopic.php?f=31&t=89826 my switch build thread (2011) https://forum.homeone.com.au/viewtopic.php?f=31&t=36569 Re: Sezza's Perth Build 346Feb 22, 2011 12:57 pm contract 10/11 prestart 04/10 slab 06/10 bricks 07/10 roof 09/10 plaster 10/10 Ceiling 10/10 LOCKUP 10/10 tiling wet areas 11/10 garage floor 11/10 PCI 12.01.11 handover 11.02.11 https://forum.homeone.com.au/viewtopic.php?f=31&t=39361&hilit=malvern+springs We are in !!! Re: Sezza's Perth Build 347Feb 22, 2011 3:51 pm Preliminary agreement 23/11 Contract 22/03 Prestart 06/04 - finalised on 30/04 Unconditional approval 10/05 Demolition 05/07 Slab 26/08 Brickwork 13/09-06/10 Roof frame started 07/10 viewtopic.php?f=31&t=32292 Re: Sezza's Perth Build 348Feb 22, 2011 3:53 pm contract 10/11 prestart 04/10 slab 06/10 bricks 07/10 roof 09/10 plaster 10/10 Ceiling 10/10 LOCKUP 10/10 tiling wet areas 11/10 garage floor 11/10 PCI 12.01.11 handover 11.02.11 https://forum.homeone.com.au/viewtopic.php?f=31&t=39361&hilit=malvern+springs We are in !!! Re: Sezza's Perth Build 349Feb 22, 2011 8:26 pm SEZZA'S BANKSIA DESIGNER viewtopic.php?f=31&t=33423 Building with SPH SOR - Baldivis. 3/5/10 Prestart 30/5/10 Final Plans Arrive 18/8/10 Siteworks 26/8/10 Slab 14/9/10-14/10/10 Bricks (2 Man Team) 25/10/10 Roof Frame and Roof Tiles 15/11/10 Rendering -Inside walls and Front of House Lock up and Locked Out!!! 10/12[/size] Re: Sezza's Perth Build 350Feb 22, 2011 8:30 pm contract 10/11 prestart 04/10 slab 06/10 bricks 07/10 roof 09/10 plaster 10/10 Ceiling 10/10 LOCKUP 10/10 tiling wet areas 11/10 garage floor 11/10 PCI 12.01.11 handover 11.02.11 https://forum.homeone.com.au/viewtopic.php?f=31&t=39361&hilit=malvern+springs We are in !!! Re: Sezza's Build SOR Perth. tiling completed. 351Feb 22, 2011 11:09 pm SEZZA'S BANKSIA DESIGNER viewtopic.php?f=31&t=33423 Building with SPH SOR - Baldivis. 3/5/10 Prestart 30/5/10 Final Plans Arrive 18/8/10 Siteworks 26/8/10 Slab 14/9/10-14/10/10 Bricks (2 Man Team) 25/10/10 Roof Frame and Roof Tiles 15/11/10 Rendering -Inside walls and Front of House Lock up and Locked Out!!! 10/12[/size] Re: Sezza's Perth Build.. what do you think??? 352Feb 23, 2011 9:34 am my new build thread- Ben Trager https://forum.homeone.com.au/viewtopic.php?f=31&t=89826 my switch build thread (2011) https://forum.homeone.com.au/viewtopic.php?f=31&t=36569 Re: Sezza's Perth Build.. what do you think??? 353Feb 23, 2011 10:24 am SEZZA'S BANKSIA DESIGNER viewtopic.php?f=31&t=33423 Building with SPH SOR - Baldivis. 3/5/10 Prestart 30/5/10 Final Plans Arrive 18/8/10 Siteworks 26/8/10 Slab 14/9/10-14/10/10 Bricks (2 Man Team) 25/10/10 Roof Frame and Roof Tiles 15/11/10 Rendering -Inside walls and Front of House Lock up and Locked Out!!! 10/12[/size] Re: Sezza's Perth Build.. 354Feb 24, 2011 9:42 am SEZZA'S BANKSIA DESIGNER viewtopic.php?f=31&t=33423 Building with SPH SOR - Baldivis. 3/5/10 Prestart 30/5/10 Final Plans Arrive 18/8/10 Siteworks 26/8/10 Slab 14/9/10-14/10/10 Bricks (2 Man Team) 25/10/10 Roof Frame and Roof Tiles 15/11/10 Rendering -Inside walls and Front of House Lock up and Locked Out!!! 10/12[/size] Re: Sezza's Build SOR Perth. tiling completed. 355Feb 24, 2011 3:01 pm Building with Life$tyle Homes in Perth SOR Key Dates on First Page of my Thread viewtopic.php?f=31&t=38761 Re: Sezza's Perth Build.. 356Feb 24, 2011 6:00 pm No more rubbish out the front!!!!! our pile was collecting all sorts, other than normal building rubbish. at one stage there was a couch, a car trye!!!! Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ we are going into the house today. looking forward to that. hopefully not too many faults to pick. and if there is hopefully they will be sorted before real PCI. and then keyzzzzzzzz......................!!!!! just found out bout the long weekend coming up in april. sat, sun, mon, tues off for me for anzac day and easter...... will be in the house by then so pefect time to get stuck into stuff!!! SEZZA'S BANKSIA DESIGNER viewtopic.php?f=31&t=33423 Building with SPH SOR - Baldivis. 3/5/10 Prestart 30/5/10 Final Plans Arrive 18/8/10 Siteworks 26/8/10 Slab 14/9/10-14/10/10 Bricks (2 Man Team) 25/10/10 Roof Frame and Roof Tiles 15/11/10 Rendering -Inside walls and Front of House Lock up and Locked Out!!! 10/12[/size] Re: Sezza's Perth Build.. inspection before real PCI today!! 357Feb 25, 2011 12:39 pm Nice clean site As to your tapware I think it will look more interesting if they will go on the site but closer to the wall - like 45 degrees from wall - if you know what I mean contract 10/11 prestart 04/10 slab 06/10 bricks 07/10 roof 09/10 plaster 10/10 Ceiling 10/10 LOCKUP 10/10 tiling wet areas 11/10 garage floor 11/10 PCI 12.01.11 handover 11.02.11 https://forum.homeone.com.au/viewtopic.php?f=31&t=39361&hilit=malvern+springs We are in !!! Re: Sezza's Perth Build.. inspection before real PCI today!! 358Feb 25, 2011 8:33 pm the taps are going to be positioned at the side of the sink but towards the back. is this the same as what you mean agabob??? SEZZA'S BANKSIA DESIGNER viewtopic.php?f=31&t=33423 Building with SPH SOR - Baldivis. 3/5/10 Prestart 30/5/10 Final Plans Arrive 18/8/10 Siteworks 26/8/10 Slab 14/9/10-14/10/10 Bricks (2 Man Team) 25/10/10 Roof Frame and Roof Tiles 15/11/10 Rendering -Inside walls and Front of House Lock up and Locked Out!!! 10/12[/size] Re: Sezza's Perth Build.. inspection before real PCI today!! 359Feb 25, 2011 8:43 pm ok... "dear house build diary!!!" today we had a walk through of the house. I guess you could call it the PCI before PCI!!! not alot to worry about that we noticed.... only things that we picked up were: 1 of the linean doors on the inside wasnt painted. on the driveway and at the path near the front door our darker boarder pavers, 1 of them is chipped and another has a defect in it. like a marble effect with limestone!!! there was a hole in one of the bedroom walls, but ths has already been patched up ceilings where they were cracked have also been fixed up. hmmmmmmm. thats all i can really think of at the moment. lights work, taps work, loos flush, garage door works. what else should i look out for?!?!?!?! SEZZA'S BANKSIA DESIGNER viewtopic.php?f=31&t=33423 Building with SPH SOR - Baldivis. 3/5/10 Prestart 30/5/10 Final Plans Arrive 18/8/10 Siteworks 26/8/10 Slab 14/9/10-14/10/10 Bricks (2 Man Team) 25/10/10 Roof Frame and Roof Tiles 15/11/10 Rendering -Inside walls and Front of House Lock up and Locked Out!!! 10/12[/size] Re: Sezza's Perth Build.. inspection before real PCI today!! 360Feb 26, 2011 1:48 am Sounds like it's all ready to go then sezza. That is quite 'generous' of your builder to have a pre-PCI inspection! Makes sense though. Take a look here for some good PCI checklists: http://www.anewhouse.com.au/?page_id=235 Built with Sw1tch H0mes >Build thread< House status 15/12: Gates and A/C finally installed! Sep 09 Bought block, Dec 09 Engaged builder, Jul '11 Moved in Thank you so much everyone. This all makes a lot of sense. I guess when you talk to a builder who butters up everything to look very polished, you get to start believing… 7 19818 1 5116 1 2897 |