Browse Forums Building A New House Re: GJ Gardner - Mandalay 298 - QLD 24May 16, 2016 3:16 pm ~Shellby~ GJ Bridgewater 203 11/3/2016 - Site Work Started 29/9/2016 - Handover 142 Work Days 6 Work Days Over https://forum.homeone.com.au/viewtopic.php?f=31&t=80174 Re: GJ Gardner - Mandalay 298 - QLD 29May 31, 2016 2:33 pm Did you get drafted plans today? I got my drafted plans one week after I paid my deposit with GJ Re: GJ Gardner - Mandalay 298 - QLD 30May 31, 2016 4:53 pm We've received preliminary plans (drafted) and made all our modifications to those (I think the 3rd one we were happy with). Our working plans have been done - and I've asked for a copy. Hopefully they'll be emailed shortly. Re: GJ Gardner - Mandalay 298 - QLD 31Jun 01, 2016 6:35 am Received the working plans soon after last reply. Mostly good. One small floorplan change to make (hinge door to cavity sliding door). However, electrical plan requires a few more changes - but it's mostly good - would like more control of myltiple lights ie. Instead of all 4 or 6 lights turning on by 1 switch I'd like to split them so I can turn 2 near TV off separately. Replace some alfresco lights (had 6) back to 2 and put one over bathroom vanities and beside pool eave and courtyard eave. Apart from these minor changes it looks good after a brief read - will print it out today and read through it properly. Re: GJ Gardner - Mandalay 298 - QLD 32Jun 01, 2016 11:59 am Not sure if your gj works like this but our csc did the electricals and when we wanted to change things he said that we can meet with the electrican and make those changes directly with him. So thats what we did. Which is good cos we didnt get their %mark up on the additions we made. Re: GJ Gardner - Mandalay 298 - QLD 33Jun 01, 2016 4:49 pm livpal5 Not sure if your gj works like this but our csc did the electricals and when we wanted to change things he said that we can meet with the electrican and make those changes directly with him. So thats what we did. Which is good cos we didnt get their %mark up on the additions we made. Thanks livpal, they worked off a preliminary electrical plan we submitted a fair while back. I don't think the prices should jump around much, it's more about moving a few existing downlights and splitting some bulk lights up (ie. 4 in to 2 by 2; 6 into a 4 + 2) and having separate switches, changing a few PPs from 300mm above floor to 1200mm, etc. I've been advised to keep these changes for the design consultant - can't see it being a big issue at all. Now, we wait for an appointment with the design consultant and hopefully some choices will be made and in a contract around this time next week! Or soon after. Re: GJ Gardner - Mandalay 298 - QLD 34Jun 05, 2016 1:57 pm Re: GJ Gardner - Mandalay 298 - QLD 35Jun 05, 2016 4:38 pm Re: GJ Gardner - Mandalay 298 - QLD 36Jun 06, 2016 7:51 pm Colours selection booked for next Wednesday (15th June). As far as I understand we will decide: Exterior Brick: Roof (and whirly birds) colour: Downpipes/eaves/fascia colour: Panel door colour: Window trimming colour: Security screen colour: Front door style and colour: Porch tiles - style/colour/code: Alfresco - style/colour/code: Interior Floor tiles - style and colour - code: Floorboards - already chosen: French Oak laminate Paint - walls/woodwork/roof/etc: Kitchen - stone colour; cupboard laminate type/colour; cupboard/draw configuration and heights; laminex type/colour; sink; tapware; splashback tiling; handles Bathroom/ensuite/powder room - each - floor tiling (same as house); wall tiling; stone colour; sink; tapware; vanity laminate type/colour; handles; feature tiling Laundry - laminex type/colour; floor tiling (same as house); splashback; cabinetry laminate type/colour and height; sink; tapware; handles Internal door types/colours: Door handles: Electrical plan: have a fairly good idea (as posted) Anything we don't know about? We're going to try and knock it all off in the one day, if we can, but don't want to stuff it up, as this is hopefully something we'll enjoy for a couple of decades. Re: GJ Gardner - Mandalay 298 - QLD 37Jun 07, 2016 8:00 am Hi Hazza, that sounds about right and your electrical looks good to to me too - very similar to our house. We're building the Mandalay 338 at the moment. One thing we are adding after reading in h1 is a data point/power point in the top of the walk in wardrobe for a router at the back of the house. Good luck with the colour selection!! I thought I was super super organised and it still took over 5 hours! Re: GJ Gardner - Mandalay 298 - QLD 38Jun 07, 2016 8:33 am Thanks Fiat. That's a good idea with the router. We feel like we're reasonably organised - have ideas for bricks, exterior colours, interior walls etc... we've got ideas for kitchen/bathrooms but willing to listen to advice... 5 hours sounds like you did really well. Have you got a thread of your build? Re: GJ Gardner - Mandalay 298 - QLD 39Jun 07, 2016 9:46 am After an unmentionable number of hours stalking H1 and the Houzz app I thought it would've been easier than it was!! Make sure you have thought about grout colours also. That's what stumped me! No - I don't have a thread. This is actually the first thread I've ever posted on May I ask why you chose not to use GJ Gardiner? I'm actually meeting with one of the sales guys tomorrow for an appointment. Definitely not signing anything yet… 3 14036 Hi all. Anyone know when the $11,000 limit was set in legislation for renovations in QLD? Ive been renovating for 5 years now and this was the limit back then. As we know,… 0 4827 Hi, I contracted a Builder to do a Garage to Bedroom + ensuite conversion (Class 1a), the Builder engaged the Certifier and Engineer and received BDA from the Certifier… 0 5672 |