Browse Forums Building A New House Re: Carlswil's Statesman Tusmore - front yard pics 1701Apr 10, 2011 4:42 pm contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Carlswil's Statesman Tusmore - front yard pics 1704Apr 19, 2011 8:05 pm Hi Tammy. Things are good, but very busy.we haven't done anymore on the house or yard. We've booked our honeymoon, and I ordered my wedding dress on the weekend. How's things with you? contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Carlswil's Statesman Tusmore - front yard pics 1705Apr 19, 2011 10:44 pm Oh, so exciting. Where is the honeymoon? Friends went to Los Vegas for theirs.. Different from the lovely beach style honeymoon. Can't wait to see your wedding photos already. Re: Carlswil's Statesman Tusmore - front yard pics 1707Apr 23, 2011 2:11 pm Cooped07 Oh, so exciting. Where is the honeymoon? Friends went to Los Vegas for theirs.. Different from the lovely beach style honeymoon. Can't wait to see your wedding photos already. Hi Tam. We are going on a 10 night cruise. I can't wait for the wedding and holiday. brb_654 Congrats on finding the dress hope we get to see of photo of you in it Hi Barb. I'm sure I'll put up a wedding photo. contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Carlswil's Statesman Tusmore - front yard pics 1708Apr 24, 2011 5:36 pm http://i833.photobucket.com/albums/zz260/raezell2/smileyvvv.gif A cruise, so relaxing I think probably one of the best ways to relax after your wedding. I really can't wait for photos of the wedding either. http://i833.photobucket.com/albums/zz260/raezell2/CATCOLOREASTERART.jpg Contracts signed Dec 09 OK to Start Sep 17 Slab Oct 6 Frame Oct 25,26 Windows and Gutters Oct 28 Bricks Nov 2 -20 Roof Finished Nov 10 Insulation and Gyprock Finished Nov 30 Locked Out Dec 13 Cupboards Installed Dec 17 Tile prep work Dec 26 Painter started Dec 30 Stormwater Jan 17 Tiles Jan 10-19 PCI Feb 2 Handover Feb 9 viewtopic.php?f=31&t=37120[size=85] Carlswil's Statesman Tusmore - front yard pics 1709May 10, 2011 3:28 pm Just stopping in to see if there are any updates! Re: Carlswil's Statesman Tusmore - front yard pics 1710May 10, 2011 4:12 pm Good to hear your new job is going well....and it's nice to work for a goal....your wedding and honeymoon...and some landscaping by the sounds of it.. Re: Carlswil's Statesman Tusmore - front yard pics 1711May 12, 2011 6:46 am I haven't really got much to update. We sent off our 3 month maintenance form to them when it was due (2 months ago). We got a letter in the mail saying that we'd been assigned to a maintenance company, and we're still waiting. Builder said this is normal. Kinda amusing given I think cooped had hers done around the day it was due. We still don't have a water meter, which is good given water prices are going up. Last time I spoke to SA water, they said they couldn't do it yet, but we wouldn't receive a bill for estimated use, so that's good. Our backyard is a mudpit. At this stage, it is going to have to wait. We're busy saving for the wedding, so no money for lawn just yet. contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Carlswil's Statesman Tusmore - front yard pics 1712May 12, 2011 1:26 pm Nice to see you back, I know work is keeping you really busy! We've been in our house over 8 months and still waiting for a few maintenance jobs to get done, it seems like maintenance is not high on a builders priority I wouldn't be complaining about not getting a bill for water, lucky you Re: Carlswil's Statesman Tusmore - front yard pics 1713May 16, 2011 1:48 pm http://i833.photobucket.com/albums/zz260/raezell2/676276knm5m6gfl5.gif just catching up on everyone's threads, I can't believe that your maintenance hasn't been done yet. I posted ours on the 8th May, next day I had a phone call and the guy came 2 days later to fix everything. We did only have a half page but still it was very quick. Even the plumber wanted to come on Friday, but it was inconvenient. I hope you get yours fixed soon. http://i833.photobucket.com/albums/zz260/raezell2/How_rude.png Did you have a lot of things? http://i833.photobucket.com/albums/zz260/raezell2/sendinghugs.gif Contracts signed Dec 09 OK to Start Sep 17 Slab Oct 6 Frame Oct 25,26 Windows and Gutters Oct 28 Bricks Nov 2 -20 Roof Finished Nov 10 Insulation and Gyprock Finished Nov 30 Locked Out Dec 13 Cupboards Installed Dec 17 Tile prep work Dec 26 Painter started Dec 30 Stormwater Jan 17 Tiles Jan 10-19 PCI Feb 2 Handover Feb 9 viewtopic.php?f=31&t=37120[size=85] Re: Carlswil's Statesman Tusmore - front yard pics 1715Jun 11, 2011 10:12 am Hi Barb, it has been a little quiet. Things have gotten so busy, I don't get much time to get on here. Our three month maintenance has been done. They fixed everything that needed fixing, which was good. Australia post finally delivers to our street, so we bought a letterbox last week. Now we just need some nice weather so we can put it in. Other than that, there's not much happening. How's things with you? contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Carlswil's Statesman Tusmore - front yard pics 1716Mar 03, 2012 8:57 pm Hi there, I just did a search of the forum for 'Vulcan Stone' benchtops and it came up with your thread. I've had a bit of a look through your thread but as there as so many pages I haven't actually been able to see if this is the benchto you went with in the end. I have chosen this colour for our home, which is currently yet to be started being built and would love to see how the finished product looks. Do you have any close up pictures you can show me? If you could post them, or let me know what page they're on that would be fantastic. Thanks heaps Kayla Re: Carlswil's Statesman Tusmore - front yard pics 1717Apr 04, 2012 12:06 pm Happy Wedding Day for tomorrow Carlswil, I hope you remember to post a photo when you are back from your Honeymoon. Site Start: 10th September, 2010 PCI : Friday 27th January, 2011. Handover: 3rd February, 2011 Build Thread: viewtopic.php?f=31&t=37677 Re: Carlswil's Statesman Tusmore - front yard pics 1718Apr 04, 2012 12:41 pm Aren't you good RING. Nice remembering! HAPPY WEDDING DAY FOR TOMORROW! Re: Carlswil's Statesman Tusmore - front yard pics 1719Apr 04, 2012 12:50 pm I didnt remember exactly, but I havent been on much lately either, you get caught up with living and nothing much seems to change with the house after you have been in for a while (mind you still heaps to do, gotta wait for the money and time to do it) and I had some time at work and wondered about all the H1ers building at the same time and decided to check their threads and found Carlswills wedding date, nearly to the day Site Start: 10th September, 2010 PCI : Friday 27th January, 2011. Handover: 3rd February, 2011 Build Thread: viewtopic.php?f=31&t=37677 Re: Carlswil's Statesman Tusmore - front yard pics 1720Apr 04, 2012 3:00 pm Thanks guys. Yep wedding day tomorrow!! I'm excited. Will post a pic when I get back. contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 there should be ss cable so you can pull up bore pump for service 1 3550 Hi all, Need some ideas for my front yard. There are a few elements where the landscaping needs to take into account: There is a slight slope forward with steps going to… 0 3961 can someone with more experience give me their insight? land is pretty much flat its pretty much at the top of a hill. left and right neighbours are flat in line with my… 0 7722 |