Browse Forums Building A New House Re: Hickinbotham Homes in SA 784Feb 22, 2011 2:37 pm contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Hickinbotham Homes in SA 785Feb 23, 2011 8:23 am 28/10/10 Frame Finished 1/11/10 Gutters and Plumbing Finished 22/11/10 Bricks Finished 23/11/10 Electrical Started 24/11/10 Insulation/Gyprock started 14/12/10 LOCKED OUT ![]() 16/12/10 Kitchen + Bathroom Cupboards delivered 1/1/11 - Engaged ![]() 27/1/11 - Kitchen In, Tiling Done, Plumbing Done and Painting Started ![]() Re: Hickinbotham Homes in SA 786Feb 23, 2011 9:27 am contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Hickinbotham Homes in SA 789Feb 23, 2011 4:56 pm Contracts signed Dec 09 OK to Start Sep 17 Slab Oct 6 Frame Oct 25,26 Windows and Gutters Oct 28 Bricks Nov 2 -20 Roof Finished Nov 10 Insulation and Gyprock Finished Nov 30 Locked Out Dec 13 Cupboards Installed Dec 17 Tile prep work Dec 26 Painter started Dec 30 Stormwater Jan 17 Tiles Jan 10-19 PCI Feb 2 Handover Feb 9 viewtopic.php?f=31&t=37120[size=85] Re: Hickinbotham Homes in SA 790Feb 25, 2011 11:22 am 28/10/10 Frame Finished 1/11/10 Gutters and Plumbing Finished 22/11/10 Bricks Finished 23/11/10 Electrical Started 24/11/10 Insulation/Gyprock started 14/12/10 LOCKED OUT ![]() 16/12/10 Kitchen + Bathroom Cupboards delivered 1/1/11 - Engaged ![]() 27/1/11 - Kitchen In, Tiling Done, Plumbing Done and Painting Started ![]() Re: Hickinbotham Homes in SA 791Feb 25, 2011 11:28 am contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Hickinbotham Homes in SA 794Mar 01, 2011 8:51 am contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Hickinbotham Homes in SA 796Mar 01, 2011 10:41 am contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Hickinbotham Homes in SA 798Mar 01, 2011 12:32 pm I'm glad you survived the move and are loving your house. Once you've got a few little Squids running around, it won't feel so big. contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Hickinbotham Homes in SA 799Mar 01, 2011 4:04 pm ![]() Could they explain why your neighbour's site cost was half of yours? How did you find out that they'd stuffed up the plan? How far have you got with the process, could you cancel the contract and go with someone else (and forgo your deposit) Thanks a lot for your reply! They said my footing is very deep because of the reactive soil. It was true but my neighbour's is a double storey and it has to meet some spec to get an approval. They had wasted me more half year time then. I was a bit desperate to have my house erected. So I signed the footing cost variation. Don't laugh at me. I only find they stuffed up the plan when I moved in. I put in some furnature, felt weird, measured the room, check the plan and found the problem. Re: Hickinbotham Homes in SA 800Mar 01, 2011 8:04 pm ![]() How are the Squids and bobbaloochies going? Hey!! Well we are all moved in. We are loving our house but hate the moving part!!! Soooo over it!! We had heaps of help though so very lucky, just finishing unpacking now. I love having an ensuite too!!! Whoo hoop! Ram I don't know how you did thi on an iPhone for so long! It's so annoying!! Can't wait to have the internet!! Chow all x I would never build with Fowler homes. I built with them in 2021 and till date maintenance issues are pending. All their existing trades and businesses don't work with… 14 110957 Hi there! Putting the feelers out there for those who have (or almost) built with Arli homes! Interested in your experiences who've built from their stock home designs… 0 27162 |