Browse Forums Building A New House Re: Who is building with Beechwood 82Feb 18, 2011 1:20 pm Our Acreage Build The Lakeview Lodge - Beechwood Homes 01/04/10 YES 2010 - Deposit paid 23/09 - PCI CANCELLED 28/09 - PCI - will it happen.-18 months later 07/10/11 - ITS OURS..WOOHOO Re: Who is building with Beechwood 83Feb 18, 2011 3:39 pm just starting Lake View Lodge - Beechwood deposit 17/08/09 Council April 10 signed contract 11/06 earthworks started 9/07 slab completed 8/09/10 Frames 21/09/10 bricking finished 13/10/10 roof 22/10/10 Gyprock 22/11/10 Tiles bathroom 21/12/10 Kitchen in 21/12/10 Painting 09/02/11 handover 11/03/11 We are in 15/03/11!!!!!!!! http://kathdom.blogspot.com/ Re: Who is building with Beechwood 84Feb 18, 2011 3:45 pm Our Acreage Build The Lakeview Lodge - Beechwood Homes 01/04/10 YES 2010 - Deposit paid 23/09 - PCI CANCELLED 28/09 - PCI - will it happen.-18 months later 07/10/11 - ITS OURS..WOOHOO Re: Who is building with Beechwood 86Feb 19, 2011 3:23 pm Our Acreage Build The Lakeview Lodge - Beechwood Homes 01/04/10 YES 2010 - Deposit paid 23/09 - PCI CANCELLED 28/09 - PCI - will it happen.-18 months later 07/10/11 - ITS OURS..WOOHOO Re: Who is building with Beechwood 88Feb 20, 2011 11:57 am Hi Penny - welcome I look forward to sharing our journeys.....very excited for you, we almost chose a Allworth also but preferred the Merlot and it came with much more interms of extra and upgrades were more reasonable we felt. Beechwood have been not too bad so far.....although I find you have to keep on them all the time to ensure it keeps moving forward, Although I cant comment on Newcastle office as we are dealing with Sydney Head Office. We really want to see a Merlot started or even completed, can I ask you to please PM me the address of the one you found today, as my hubby is a sales rep around the Newcastle/Maitland area and would like to go and have a look. Acre - Hope you get some action this week. I am going to call them again tomorrow and get an update....squeaky wheels always get oiled IYKWIM.... Cheers.... Land Settlement - 1/10/10 Slab 23/3 Frame 14/04 Roof Tiling 29/4 Bricks 5/5 Electrical Rough In 27/5 Gyprocking 23/6 Kitchen install 29/6 Tiles 14/7 Paint 4/8 Plumbing 27/7 Were in 1/9 Re: Who is building with Beechwood 89Feb 20, 2011 6:13 pm haha we are actually renting in Aberglasslyn, nr mckechies. We are going through Beresfield office, They have been good i must admit - its just there time frame thats annoying. Our Acreage Build The Lakeview Lodge - Beechwood Homes 01/04/10 YES 2010 - Deposit paid 23/09 - PCI CANCELLED 28/09 - PCI - will it happen.-18 months later 07/10/11 - ITS OURS..WOOHOO Re: Who is building with Beechwood 90Feb 21, 2011 7:02 am Thought I would share our floor plan....goodness this is about the 5th attempt...hope it works this time! Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Land Settlement - 1/10/10 Slab 23/3 Frame 14/04 Roof Tiling 29/4 Bricks 5/5 Electrical Rough In 27/5 Gyprocking 23/6 Kitchen install 29/6 Tiles 14/7 Paint 4/8 Plumbing 27/7 Were in 1/9 Re: Who is building with Beechwood 91Feb 21, 2011 8:38 am Jacknruby - house plan looks great hopefully all will be progressing soon Amanda - how's it all going??? any movement of soil yet Penny - nice to see you join the "beechwood family" Got the final price today turned out cheaper than we thought. Settlement should be done on Thursday how long has this taken But everything aside.........the house is ready and beechwood have done a fantastic job overall Need to have the tiles and carpet put in yet and they are going to wait for the tiles to go in before they put in the applicances. Tiler starts on 28th Feb.....should take about 7 days for the tiler......1 day for the carpet......hopefully should be moving in during the week of 13th March......in time for my husbands 40th birthday on the 19th and my sons 13th birthday on the 21st just starting Lake View Lodge - Beechwood deposit 17/08/09 Council April 10 signed contract 11/06 earthworks started 9/07 slab completed 8/09/10 Frames 21/09/10 bricking finished 13/10/10 roof 22/10/10 Gyprock 22/11/10 Tiles bathroom 21/12/10 Kitchen in 21/12/10 Painting 09/02/11 handover 11/03/11 We are in 15/03/11!!!!!!!! http://kathdom.blogspot.com/ Re: Who is building with Beechwood 92Feb 21, 2011 8:46 am Kathy, Sounds fantastic, so so jealous. Ill be calling beechwood shortly, so ill let you know what they say. Our Acreage Build The Lakeview Lodge - Beechwood Homes 01/04/10 YES 2010 - Deposit paid 23/09 - PCI CANCELLED 28/09 - PCI - will it happen.-18 months later 07/10/11 - ITS OURS..WOOHOO Re: Who is building with Beechwood 93Feb 22, 2011 5:46 pm Mission Accomplished ! I have seen a finished Merot! The family room was bigger than i thought and the Rumpus. It is great to see all the progress and read about everyones news. I hope it wont be long and i can put up pictures but i know it will be a while as we are only up to the quote stage. Well good luck to all and i will look forward to updates. Penny Paid deposit-22/3/11 Plans ready and signed off 23/4/11 Plans submitted to Council 23/5/11 Plans received in post 31/5/11 Contracts signed 3/6/11 Ready for slab 8/8/11 Finished and in 19/12/11 Re: Who is building with Beechwood 94Feb 23, 2011 6:56 am Clean up crew were in yesterday Sent away final payment today Tiler starts on Monday Carpet is booked in for 10th March just starting Lake View Lodge - Beechwood deposit 17/08/09 Council April 10 signed contract 11/06 earthworks started 9/07 slab completed 8/09/10 Frames 21/09/10 bricking finished 13/10/10 roof 22/10/10 Gyprock 22/11/10 Tiles bathroom 21/12/10 Kitchen in 21/12/10 Painting 09/02/11 handover 11/03/11 We are in 15/03/11!!!!!!!! http://kathdom.blogspot.com/ Re: Who is building with Beechwood 95Feb 23, 2011 2:09 pm Kathy, Its finally your turn - what a journey you have had. I cant wait to see more pictures. What did you end up choosing for your tiles? We are hoping to have siteworks next weeks. hopeso. (28 days is up this week) (28working days is up next week) so either way work is meant to start next week. Our Acreage Build The Lakeview Lodge - Beechwood Homes 01/04/10 YES 2010 - Deposit paid 23/09 - PCI CANCELLED 28/09 - PCI - will it happen.-18 months later 07/10/11 - ITS OURS..WOOHOO Re: Who is building with Beechwood 96Feb 24, 2011 2:21 pm We chose tile from the Tile Market in smithfield in Sydney, we got 100 square metres for $2000.00 The tiles are creamy to white colour and are 600 x 600 should look really nice when laid. Start is Monday. Did you get pebblecrete on the front verandah?? It was one of our extras.....I'll send you some photos later. Any movement yet just starting Lake View Lodge - Beechwood deposit 17/08/09 Council April 10 signed contract 11/06 earthworks started 9/07 slab completed 8/09/10 Frames 21/09/10 bricking finished 13/10/10 roof 22/10/10 Gyprock 22/11/10 Tiles bathroom 21/12/10 Kitchen in 21/12/10 Painting 09/02/11 handover 11/03/11 We are in 15/03/11!!!!!!!! http://kathdom.blogspot.com/ Re: Who is building with Beechwood 97Feb 24, 2011 2:41 pm Hi Just starting, Very happy for you, we're just starting, our slab was finished on 16.02.11 We must have got the same creamy porcelain 600x600 tiles, great place Tile Mart aren't they? I'd be interested to see what the tiles look like once they're laid, did you have any probs finding a tiler to do the tiling? If you get the chance it would be nice to see pics of the tiles laid Re: Who is building with Beechwood 98Feb 24, 2011 3:02 pm Kathy, i called them yesty and should be starting next week. heres hoping. No we went tiles on the verandah. we will have the same kinda tile from the verandah, through the house through to the alfresco. Did you go pebblecrete on the verandah? we are going white, black, and greys through the house (with red kitchen splashback) with bits of red around the living rooms, So although we havent chosen our internal tiles we will be going with a 600x600 whitish grey tiles. Have you got anymore pics from today? did today go smoothly? how many weeks from when they started on site did it take? When i spoke to beechwood yesty the lady who i always talk to that they will make up for time whilst on site so im hoping that means they will complete sooner than the 23weeks (unless we have wet weather) Our Acreage Build The Lakeview Lodge - Beechwood Homes 01/04/10 YES 2010 - Deposit paid 23/09 - PCI CANCELLED 28/09 - PCI - will it happen.-18 months later 07/10/11 - ITS OURS..WOOHOO Re: Who is building with Beechwood 99Feb 24, 2011 3:17 pm Hi all Just Starting - Congrats on your settlement.....hope it all went smoothly. Cant wait to see the final pics... Acre - its really disappointing isnt it, but I am learning not to expect anything as it you just get let down on the end..... Although I have been in email war asking for commencement and they cant give me a date but we are 15 days into the contract so another 13 days to start.....but they advised benching has been done so my hubby is going to check our block this afternoon hopefully they done it and its a start....next is the piers.....god hope they dont find rock or anything else that may cost more $$$..... Springtime - hi, how long from benching till the slab was laid? cant wait for ours to be laid.....this will feel like we are moving and not stationary. Land Settlement - 1/10/10 Slab 23/3 Frame 14/04 Roof Tiling 29/4 Bricks 5/5 Electrical Rough In 27/5 Gyprocking 23/6 Kitchen install 29/6 Tiles 14/7 Paint 4/8 Plumbing 27/7 Were in 1/9 Re: Who is building with Beechwood 100Feb 24, 2011 4:10 pm Whats Benching? Our 28 days is up on Monday so we can only hope Our Acreage Build The Lakeview Lodge - Beechwood Homes 01/04/10 YES 2010 - Deposit paid 23/09 - PCI CANCELLED 28/09 - PCI - will it happen.-18 months later 07/10/11 - ITS OURS..WOOHOO Hey guys building a new place through a volume builder and just wondering if i should complain to the site supervisor as we just had plasterboard installed. Looks like… 0 11828 Elvis has left the building... The site supervisor quit after 2 month on the project. I guess he was just instructed to bark at people, but didn't like when he was… 26 21618 |