Concreted my alfresco area which is under the main roof. It was a strip footing originally, i have since had approx. 150mm concrete floor poured ontop. Issue is it was laser level and 12months on its raised approx. 5mm ? compared to house foundation.
What is the cause? Remembering its poured ontop of a strip footing connected to the house foundation.