Browse Forums Building A New House Re: Building with Wisdom Homes 15675Mar 30, 2020 5:31 pm Just had my second PC inspection today. Other than a few minor issues (which they will fix promptly) looks like everything else has been fixed to a reasonable standard. Now I have a new issue which has come up. My bank (NAB) requires an interim occupation certificate before releasing the final payment. Wisdom's certifiers are claiming that I need to get the driveway (and a few other things) done before they can issue the certificate. The things they are saying I need to do are all items which will be completed after handover by my landscaper. I believe they have misinterpreted my DA requirements. The bank does not agree that those items need to be done before the interim certificate can be issued so is refusing to release the funds. I have gone back and forth with my CSR on this issue and have asked her to escalate it to her manager. Has anyone else had this issue? Re: Building with Wisdom Homes 15677Mar 31, 2020 8:57 pm Funk52 Just had my second PC inspection today. Other than a few minor issues (which they will fix promptly) looks like everything else has been fixed to a reasonable standard. Now I have a new issue which has come up. My bank (NAB) requires an interim occupation certificate before releasing the final payment. Wisdom's certifiers are claiming that I need to get the driveway (and a few other things) done before they can issue the certificate. The things they are saying I need to do are all items which will be completed after handover by my landscaper. I believe they have misinterpreted my DA requirements. The bank does not agree that those items need to be done before the interim certificate can be issued so is refusing to release the funds. I have gone back and forth with my CSR on this issue and have asked her to escalate it to her manager. Has anyone else had this issue? That’s interesting. I thought the interim OC no longer exist ..?? Re: Building with Wisdom Homes 15678Mar 31, 2020 9:00 pm BigD Wisdom Landscape Voucher What are people using their free(?) voucher for?? Tough choice what to do eh, the quotes so far seem rather expensive compared to other landscapers. If their cost was just a tad more than the market, they would have much more business. I’m considering to do one side of my fence as it needs replacing. Re: Building with Wisdom Homes 15679Mar 31, 2020 9:01 pm faykis Manhattan52 @faykis You would probably need to PM Mark rather than comment on the forum about your particular issue Are you waiting on your tender in order to seek your full approval for finance? Typically you would need a signed contract, end panel and council or CDC approved plans for your approval. This does differ between lenders though We have pre approval for building loan. Already have land loan running with the same bank. Our bank said they’ll give us A conditional approval based on a fixed price tender including plans n inclusions. Then full unconditional approval with CDC approved plans. Any extra selection choices may or may not be considered by the bank later on depending on situation and we may have to be prepared to pay post tender variations out of pocket. We cant risk waiting for 30/4 thats too late to sign, then wait for the bank to do building valuation that late. valuation may come low at that time looking at the way the economy is going. We spoke to our broker (direct from bank) yesterday and he said if we can get the fixed price tender in now the building valuation should be ok if done this month/ quicker, he cant comment on how things may turn out if we have to wait till May. Did you end up having your tender moved to a closer date? Re: Building with Wisdom Homes 15680Mar 31, 2020 9:13 pm Ambassador36 How is everyone tracking with their builds? We had the frames inspection yesterday which was exciting but we are unsure how the rest of our build will progress in the current climate. Stay safe everyone Fortunately the construction industry is still running! Our build has been slower than I like in the last 2 months and believe it comes down to lack of tradies available. Got a house down the street (would have went with that volume builder but was told they don’t build in my area 😳 ) that did their slab while we were in the framing stage. Now they are ahead in the internal stage and yes, similar size house. One thing I realised is regardless if your frames are bowed or plumb during the inspection, they won’t be fixed until the last possible minute before the plasterboard. Guess that’s ok ... as long as it is fixed. Can someone please offer some advice? Im DESPERATE. Because I'm completely and utterly exhausted. How long are variations taking with other companies at the moment? We… 0 19434 In fairness nobody gave a crap about the ACCC and the gag clauses continued in the pro forma templates of a few other builders after the ACCC took on Wisdom, and more… 19 75063 Hi Everyone, I am exploring builder in NSW and received a very tempting quote from Wisdom home for their momentum series. I just want to know experience of building… 0 9809 |