After calculating rain days From BOM and shutdowns for Xmas as well as extension of time for building variations would be a few weeks over which is pretty good considering the scope of landscaping works being undertaken
Glad you are happy with it 😆
How do you calculate rain days from BOM? Is it rain over a certain amount? I also didn’t know there is time extension for building variations. We have some but hopefully not too significant for delays. Were you informed of how much time would be factored in for these building variations? We are hesitant to do further landscaping works with Wisdom as we really don’t want to take any longer to move in. Still undecided... Can we move in without a driveway?
No wasn’t told how long the extension of time was but just used the time it took as a rough guide.
I used a 2mm and over filter on the BOM site.
Your driveway will depend on any DA or approval requirements.