Then next question is - if we want to save / organise rental etc, do we have 9 months before demolition? And 9 months from what - tender acceptance? The 1k? The plan acceptance?
For context we are a doing a KDRB
For tender presentation, between 2 to 4 weeks as they need to do surveys and do accurate costing.
For plan acceptance, it will depend on how big and how many changes you make to your design. could be a few weeks if no changes to several months if you keep changing it.
Demo takes about a month and they usually start build a few weeks after Demo clearance certificate is provided, so plan acceptance is when everything is locked in and you will need to do the selections. Moving out 9 months from plan acceptance is a reasonable assumption.
Thank you for that info. I just wanted to know what it is contractually. Like H&H might be ready to start construction and we aren’t. They said I had 9 mths before you have to pay $1200 a month for delay - but 9 months from
When? I’ve asked a few times and can’t get clear answer