After your LACC approval your file will then be wrapped up and moved to production estimates. This is where they start ordering everything for site start. A site fence will appear and also a portaloo.
melindaz
Really depends on so many things.
- How long your bank takes
- your build as everyone has a different site
- Any landscape/pool works that need to be done prior to slab
From the time you have given bank approval maybe a month until you get your site scraped/excavated etc. it’s hard to say as everyone has a different and unique project
For example I moved into production estimating on first week of October and my slab was poured 16th November. I am currently at framing stage
Hope that helps