Date | |
Contract of Sale - land signed | 12/11/2016 |
Settlement of land | 01/11/2017 |
Land title transfer | 23/11/2017 |
Planning permit approval | 10/04/2018 |
Builder - Metricon | |
Request for preliminary contract signed | 09/11/2016 |
Initial Deposit | 11/11/2016 |
Soil test report | 18/11/2016 |
Preliminary contract signed | 21/03/2017 |
PC deposit | 21/03/2017 |
Electrical selection | 04/05/2017 |
Studio M & Tile selection | 05/05/2017 |
Contract signed | 04/08/2017 |
Building permit approval | 30/04/2018 |
Site work started | 18/06/2018 |