Browse Forums Building A New House Re: Building Mainvue Aegean430 - 45sq in Berwick Waters 162Nov 12, 2017 12:30 pm follow my build Arden homes Votivo 37 iin south east: https://forum.homeone.com.au/viewtopic.php?f=31&t=88622 Building Mainvue Aegean430 - 45sq in Berwick Waters 168Nov 13, 2017 7:33 pm Framing has finally finished! Took 3.5 weeks so hoping they’ve done a good job. Frame & slab inspection booked for 9am Wednesday 🤞🏼 Gutters & Facia have been delivered but no windows or bricks yet, probably best as there’s been heaps of theft on ours and surrounding blocks. Our Henley Aegean45 Re: Building Mainvue Aegean430 - 45sq in Berwick Waters 169Nov 13, 2017 7:36 pm Aegean430 Framing has finally finished! Took 3.5 weeks so hoping they’ve done a good job. Frame & slab inspection booked for 9am Wednesday 🤞🏼 Our Henley Aegean45 That’s good - hope everything is good so that they can start the roof ASAP - follow my build Arden homes Votivo 37 iin south east: https://forum.homeone.com.au/viewtopic.php?f=31&t=88622 Re: Building Mainvue Aegean430 - 45sq in Berwick Waters 170Nov 13, 2017 7:40 pm pEast Aegean430 Framing has finally finished! Took 3.5 weeks so hoping they’ve done a good job. Frame & slab inspection booked for 9am Wednesday 🤞🏼 Our Henley Aegean45 That’s good - hope everything is good so that they can start the roof ASAP - Me too pEast! I bet the rain forecast for later this week will get in just before that tho. I feel like I’ve constantly got my fingers crossed! Our Henley Aegean45 Re: Building Mainvue Aegean430 - 45sq in Berwick Waters 171Nov 13, 2017 8:33 pm Aegean430 pEast Aegean430 Framing has finally finished! Took 3.5 weeks so hoping they’ve done a good job. Frame & slab inspection booked for 9am Wednesday 🤞🏼 Our Henley Aegean45 That’s good - hope everything is good so that they can start the roof ASAP - Me too pEast! I bet the rain forecast for later this week will get in just before that tho. I feel like I’ve constantly got my fingers crossed! Our Henley Aegean45 Yeah that 2 weeks delay and u would have the roof from the rain - I have slab for Friday and now with rain maybe next week follow my build Arden homes Votivo 37 iin south east: https://forum.homeone.com.au/viewtopic.php?f=31&t=88622 Re: Building Mainvue Aegean430 - 45sq in Berwick Waters 172Nov 14, 2017 12:42 pm pEast Aegean430 pEast [quote="Aegean430"]Framing has finally finished! Took 3.5 weeks so hoping they’ve done a good job. Frame & slab inspection booked for 9am Wednesday 🤞🏼 Our Henley Aegean45 That’s good - hope everything is good so that they can start the roof ASAP - Me too pEast! I bet the rain forecast for later this week will get in just before that tho. I feel like I’ve constantly got my fingers crossed! Our Henley Aegean45 Yeah that 2 weeks delay and u would have the roof from the rain - I have slab for Friday and now with rain maybe next week[/quote] Yes better to wait for dry weather for the slab, but I’ve seen them done when it’s lightly raining. Hopefully the weather app on my phone is wrong, it says 2 sunny days in the next 9 Our Henley Aegean45 Re: Building Mainvue Aegean430 - 45sq in Berwick Waters 173Nov 14, 2017 1:34 pm I hope too cos got slab this Friday follow my build Arden homes Votivo 37 iin south east: https://forum.homeone.com.au/viewtopic.php?f=31&t=88622 Building Mainvue Aegean430 - 45sq in Berwick Waters 174Nov 20, 2017 7:20 pm Start of Week 10 & the windows, door and stacker door frames have been delivered. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Looks like the delivery guys were a big heavy handed and have split the wood on one of the sliding door frames. I’ve let the SS know and he’s teeing up a new one with the supplier. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ The frame inspection was also done last week and a few issues were found such as some walls out of plumb, floor not level in areas, some bulkheads not level and some overhang >10mm of frame to the slab - all marked with pink spray paint. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ On a progressive note, the heating unit and ducting has been roughed in, although I’ve noticed the 2 vents in the family room are in the wrong spot. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ The colorbond roof in Monument is 95% done, including sarking which I think is a great inclusion. Oh yes, and front door, garage/internal door and laundry door frames are all installed with temp doors - will try to grab some more pics tomorrow. Our Henley Aegean45 Re: Building Mainvue Aegean430 - 45sq in Berwick Waters 175Nov 20, 2017 7:33 pm Aegean430 Start of Week 10 & the windows, door and stacker door frames have been delivered. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Looks like the delivery guys were a big heavy handed and have split the wood on one of the sliding door frames. I’ve let the SS know and he’s teeing up a new one with the supplier. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ The frame inspection was also done last week and a few issues were found such as some walls out of plumb, floor not level in areas, some bulkheads not level and some overhang >10mm of frame to the slab - all marked with pink spray paint. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ On a progressive note, the heating unit and ducting has been roughed in, although I’ve noticed the 2 vents in the family room are in the wrong spot. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ The colorbond roof in Monument is 95% done, including sarking which I think is a great inclusion. Oh yes, and front door, garage/internal door and laundry door frames are all installed with temp doors - will try to grab some more pics tomorrow. Our Henley Aegean45 Good progress now follow my build Arden homes Votivo 37 iin south east: https://forum.homeone.com.au/viewtopic.php?f=31&t=88622 Re: Building Mainvue Aegean430 - 45sq in Berwick Waters 176Nov 20, 2017 7:38 pm pEast Aegean430 Start of Week 10 & the windows, door and stacker door frames have been delivered. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Looks like the delivery guys were a big heavy handed and have split the wood on one of the sliding door frames. I’ve let the SS know and he’s teeing up a new one with the supplier. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ The frame inspection was also done last week and a few issues were found such as some walls out of plumb, floor not level in areas, some bulkheads not level and some overhang >10mm of frame to the slab - all marked with pink spray paint. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ On a progressive note, the heating unit and ducting has been roughed in, although I’ve noticed the 2 vents in the family room are in the wrong spot. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ The colorbond roof in Monument is 95% done, including sarking which I think is a great inclusion. Oh yes, and front door, garage/internal door and laundry door frames are all installed with temp doors - will try to grab some more pics tomorrow. Our Henley Aegean45 Good progress now Getting there.... How did ur slab go? Our Henley Aegean45 Re: Building Mainvue Aegean430 - 45sq in Berwick Waters 177Nov 20, 2017 7:41 pm Aegean430 pEast Aegean430 Start of Week 10 & the windows, door and stacker door frames have been delivered. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Looks like the delivery guys were a big heavy handed and have split the wood on one of the sliding door frames. I’ve let the SS know and he’s teeing up a new one with the supplier. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ The frame inspection was also done last week and a few issues were found such as some walls out of plumb, floor not level in areas, some bulkheads not level and some overhang >10mm of frame to the slab - all marked with pink spray paint. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ On a progressive note, the heating unit and ducting has been roughed in, although I’ve noticed the 2 vents in the family room are in the wrong spot. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ The colorbond roof in Monument is 95% done, including sarking which I think is a great inclusion. Oh yes, and front door, garage/internal door and laundry door frames are all installed with temp doors - will try to grab some more pics tomorrow. Our Henley Aegean45 Good progress now Getting there.... How did ur slab go? Our Henley Aegean45 Sorry for posting on ur site - here it is done on Friday Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ follow my build Arden homes Votivo 37 iin south east: https://forum.homeone.com.au/viewtopic.php?f=31&t=88622 Re: Building Mainvue Aegean430 - 45sq in Berwick Waters 178Nov 20, 2017 7:53 pm pEast Aegean430 pEast [quote="Aegean430"]Start of Week 10 & the windows, door and stacker door frames have been delivered. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Looks like the delivery guys were a big heavy handed and have split the wood on one of the sliding door frames. I’ve let the SS know and he’s teeing up a new one with the supplier. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ The frame inspection was also done last week and a few issues were found such as some walls out of plumb, floor not level in areas, some bulkheads not level and some overhang >10mm of frame to the slab - all marked with pink spray paint. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ On a progressive note, the heating unit and ducting has been roughed in, although I’ve noticed the 2 vents in the family room are in the wrong spot. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ The colorbond roof in Monument is 95% done, including sarking which I think is a great inclusion. Oh yes, and front door, garage/internal door and laundry door frames are all installed with temp doors - will try to grab some more pics tomorrow. Our Henley Aegean45 Good progress now Getting there.... How did ur slab go? Our Henley Aegean45 Sorry for posting on ur site - here it is done on Friday Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ [/quote] Awesome! And don’t be sorry, u can post anything u like Once the frame gets going it’s great to get a feel for all the rooms. Our Henley Aegean45 Re: Building Mainvue Aegean430 - 45sq in Berwick Waters 179Nov 21, 2017 6:29 am Aegean430 Start of Week 10 & the windows, door and stacker door frames have been delivered. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Looks like the delivery guys were a big heavy handed and have split the wood on one of the sliding door frames. I’ve let the SS know and he’s teeing up a new one with the supplier. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ The frame inspection was also done last week and a few issues were found such as some walls out of plumb, floor not level in areas, some bulkheads not level and some overhang >10mm of frame to the slab - all marked with pink spray paint. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ On a progressive note, the heating unit and ducting has been roughed in, although I’ve noticed the 2 vents in the family room are in the wrong spot. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ The colorbond roof in Monument is 95% done, including sarking which I think is a great inclusion. Oh yes, and front door, garage/internal door and laundry door frames are all installed with temp doors - will try to grab some more pics tomorrow. Our Henley Aegean45 Hi Aegean, I love watching your build grow. I can't believe that the delivery people were rough with your doors that's just shocking. We also go our windows, stackers and some of the external doors and frames delivered yesterday. Must have been the Aegean delivery day How's the roof going, would love to see a pic as we also are doing Monument. Happy building and I hope that all the issues are sorted quickly so that you can move forward. Re: Building Mainvue Aegean430 - 45sq in Berwick Waters 180Nov 21, 2017 9:48 am Rachael13 Aegean430 Start of Week 10 & the windows, door and stacker door frames have been delivered. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Looks like the delivery guys were a big heavy handed and have split the wood on one of the sliding door frames. I’ve let the SS know and he’s teeing up a new one with the supplier. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ The frame inspection was also done last week and a few issues were found such as some walls out of plumb, floor not level in areas, some bulkheads not level and some overhang >10mm of frame to the slab - all marked with pink spray paint. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ On a progressive note, the heating unit and ducting has been roughed in, although I’ve noticed the 2 vents in the family room are in the wrong spot. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ The colorbond roof in Monument is 95% done, including sarking which I think is a great inclusion. Oh yes, and front door, garage/internal door and laundry door frames are all installed with temp doors - will try to grab some more pics tomorrow. Our Henley Aegean45 Hi Aegean, I love watching your build grow. I can't believe that the delivery people were rough with your doors that's just shocking. We also go our windows, stackers and some of the external doors and frames delivered yesterday. Must have been the Aegean delivery day How's the roof going, would love to see a pic as we also are doing Monument. Happy building and I hope that all the issues are sorted quickly so that you can move forward. Thanks Rachel, Our houses are happening at the same time, it’ll be interesting to see if things keep progressing that way. I’ll pop past after work to take some pics of the roof. Hopefully some windows might be in too. Looking forward to the bricks getting done. Our Henley Aegean45 Hey guys building a new place through a volume builder and just wondering if i should complain to the site supervisor as we just had plasterboard installed. Looks like… 0 11798 Elvis has left the building... The site supervisor quit after 2 month on the project. I guess he was just instructed to bark at people, but didn't like when he was… 26 21565 |