I'm quite disappointed that no work happened on my build in the last 2 weeks. My SS said the bricklayer is caught up on another job so they'll do roof first but nothing happened in the first week. I chased him up the next week and asked him the plan/schedule for the week, he gave me dates but nothing really happened on those dates. Lost 2 weeks without any progress.
Have you experienced this type of delays? Is this just normal and am I freaking out?
Would love to hear what have you done or what would you do in this type of situation? eg.) Ask SS on the plan to catch up / sit tight expecting work to happen next week / just relax..
Thanks for your time and happy weekend everyone
My 2 cents:
You have a contract length. If the work is not completed within that time and there is no reason for extra days to be added as per your contract, then you will be payed the daily rate (hopefully) for exceeding the contract length. If they have wasted 2 weeks not doing anything, then I would assume they'll catch up.
Just keep a diary of everything that happens. From what I've read from many others (we haven't started yet) there are many periods of time where work just stalls.
Others may have different advice.
I understand your disappointment!