After reading through quite a few threads I think it's time to dip my toes in the water here. We're right at the beginning of the process; we have purchased land in south east Melbourne but it isn't due to title until November (and hopefully doesn't run late).
After looking at the Merricks, we went with the Winchester 28 as the master is larger and we didn't see the need for three loungerooms. The smaller footprint also means we will have a decent backyard on our 420sqm block. We're going with the basic Aspire facade to keep costs down and splurging instead on a few upgrades.
We've added on the outdoor room at the back and increased the shower in the ensuite, and added the window splashback to the kitchen (which was strangely cheaper than adding a glass splashback).
We've done a tour of Studio M already so just waiting for it all to progress to the next stage now.
Timeline:
25/2/17: first appointment with Metricon (paid holding deposit)
3/3/17: second appointment with Metricon
19/3/17: signed land contract, paid deposit
6/6/17: got married!
7/6/17: sale officially accepted
29/7/17: Studio M selections
2/8/17: Electrical appointment
6/9/17: cancelled contract appointment (docs not ready)
3/10/17: contract appointment
22/11/17: loan application submitted
9/1/18: SOC issued
15/1/18: land titled
29/1/18: settlement
14/2/18: revised plans submitted to Estate review panel
16/2/18: developer approval received
14/3/18: final colours signed off
29/3/18: final electricals signed off
4/4/18: final plans due
6/4/18: final plans signed off
12/4/18: build permit approved
13/4/18: handed over to construction (with one variation pending)
3/5/18: final date to commence as per contract but have gone back to engineering to add in stud walls
10/5/18: Notice to comply from council
16/5/18: site cut completed
23/5/18: slab poured
19/6/18: framing complete
24/6/18: fascias and gutters done, plumbing roughed in
25/6/18: roofing done, windows in
14/7/18: bricking mostly complete
20/7/18: plaster complete
27/7/18: cabinetry complete
30/7/18: lock up complete
31/7/18: fixing complete
28/8/18: tiling complete
2/9/18: electrical and plumbing fitoff complete
14/9/18: PCI
24/10/18: Occupancy certificate received
9/11/18: HANDOVER!