Hi everyone,
I thought I'd start a thread for our build.
We are building the Statesman Felixstow Alfresco in Two Wells, SA.
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
We have chosen:
Bricks: Austral Muscat Grey
Roof, Gutters, Fascia & Downpipes: Colorbond Wallaby
Roller Door & Front Doors: Shale Grey
Piers: Stack Stone with Shale Grey Render in between.
I will upload some photos when I get a chance of our selections.
We are awaiting council approval currently. This was delayed as we decided to source our own septic system (an OzziKleen system), so we needed to source our own engineering report to reflect a different system!
Looking forward to updating you all with photos.
Our timeline so far:
22 October 2016 - Signed builders agreement
24 October 2016 - Signed land contract
2 February 2017 - Colour selections
8 February 2017 - Footings report received - under budget YAY!
23 February 2017 - Final Master Plans & 'Build Pack' received - awaiting formal finance approval