Hi all, like many of H1 people, we (mainly I) have been reading (aka stalking) many posts especially those who use Redink as we are also building with them, and I think perhaps I should start my own thread. Just that I found so many helpful advices here that I feel it'll be great to part of it. We bought a 740msq block and demolished the old house. Build timeline is below.
Colorbond roof is next and we are hoping the roof will be finished by end of this week or early next. Fingers crossed.
So far we've been quite happy with RI, sales William Scates was helpful, prestart lady Sam was good, CLO and SS both appear to be quite prompt in attending to our queries.
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Time line:
26/04/2015 Signed PCQ
12/08/2015 pre start
06/11/2015 site work starts
16/11/2015 slab down
25/11/2015 bricks and frames delivered
01/01/2016 brickwork complete
13/01/2016 roof timbre delivered
14/01/2016 roof work start
25/01/2016 roof frame complete, downpipes, gutter, fascia all done
29/01/2016 roof complete
03/02/2016 grey float start
05/02/2016 grey float finish
22/02/2016 ceiling, cornice
25/02/2016 LOCK UP
26/02/2016 Cupboards in

pidge.72