Cornice was complete except they missed one built in and the kitchen bulkhead. These were completed this week.
Kitchen went in as well before xmas.
Bathrooms were water proofed also. We were suppose to be tiles before xmas, tiler was booked but picked up that the tile company order in the wrong bathroom floor tiles.
Then to find out that they are on back order and wouldn't arrive in site until mid Jan.
This was disappointing but was happy to wait. Now we have passed mid Jan and still no tiles.
![](https://s3.amazonaws.com/tapatalk-emoji/emoji35.png)
But did get a nice surprise this week having the painters show up. They have begun filling and prepping.
Anyways just happy to have something happening. Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ our split
Water tank and garage door were also installed before xmas