Browse Forums Building A New House Re: Spring Farm Riverside *Stage 42 - Ridgeview* 638Mar 16, 2015 5:26 pm The Ebs Well I can understand the work being completed maybe a week to a week and a half late but surely we have had any more rain than that! Too right! I am beginning to wonder what the hold up is. You never know, things might speed along by the end of this week...........fingers crossed. Re: Spring Farm Riverside *Stage 42 - Ridgeview* 639Mar 16, 2015 5:49 pm Yeah I agree 100%, by the end of this week, work SHOULD be completed. Has anyone had a good look at the work that has been done to the lake and compared it with what's required in VPA? Re: Spring Farm Riverside *Stage 42 - Ridgeview* 640Mar 16, 2015 6:00 pm When hubby and I went out there today, we drove to Spring Farm Drive to look at the lake and the progress, but I am not too sure how much work has been completed in accordance with the VPA requirements. I do recall Cornish stating in their December email that the bridge crossing was meant to commence 2 February. I think they have put the foundations down, but that is all! I hope that is not going to be a deal breaker in the VPA! Soak wells and electrical run in happening this week! Summit has told me they will relocate the laundry plumbing after the walls are completed. I'm actually pretty happy… 13 37291 DIY, Home Maintenance & Repair We purchased a 1960s property that is on timber stumps mostly, and a newer section is on concrete stumps. We had a building inspection initially and they reported some… 0 13683 The fastest thing a builder will do is bank your cheque, those systems work perfectly with lightning speed, everything else is slow burn. Just the way it is. 1 9495 |