Construction Timeline:
2019
August - Site work and slab stage
September/October - Brickwork
October - Upper floor truss installed
Our brickwork is near completion and we will be meeting our site supervisor soon. The images may look shocking but the walls will be rendered.Does anyone have thoughts on what we should discuss with the site supervisor or the workmanship of the brickwork?ThanksFront of house and mess (external)Lounge/front (internal)
Lounge room wall adjacent front door
Master bedroom
Laundry wall (exposed brick)
How is your build progressing?
Thanks amilelka, that's reassuring to know.
How is your build progressing?
How is your build progressing?
Upper floor truss system delivered and installed. Should be complete by early next week.
Thanks amilelka, that's reassuring to know.
How is your build progressing?
How is your build progressing?
We're shuffling along comfortably. We can almost see the end of the build in sight, but getting overwhelmed with all the things we need to do post handover!
That's great. Can't wait to see your interior.
Do you have a post handover to do list? Would be handy for me to start planning. This is our first build and its been a steep continuous learning curve that doesn't seem to end
Our upper floor truss is completed and the plasterers were there today to render the front elevation.
Fast forward 4 weeks and we have the upper frame and roof structure installed.
Related
5/02/2024
0
Hi there, We’ve recently had plans approved to add a 1st storey addition to our existing house for a growing family in Sydney. With the current cost of building…
6/10/2023
0
Can anyone give me any onfo on New Homes WA? Good or bad, hopefully good just need to know if my choice was good or not? Thanks ❤️
15/08/2023
9