Browse Forums Building A New House Re: How long did your plans take in Council? 7May 25, 2010 9:34 pm Built a Tribeca 44 with the Big M Sales Accept 15/06/09, Contract Signed 24/09/09, Site Start 23/11/09, Slab 11/12/09, Frame 12/01/10, Roof 20/01/10, Lock-up 30/03/10, Fixing 30/04/10, Handover 27/08/10. Re: How long did your plans take in Council? 9May 25, 2010 10:14 pm http://take2-customdesigndownslope.blogspot.com 07-10-09 omg they have cut the block 14-05-10 we finally have the keys Re: How long did your plans take in Council? 11May 25, 2010 10:22 pm Building the Monte Carlo with McD Jones View my building thread @ viewtopic.php?f=31&t=37255 Re: How long did your plans take in Council? 15Aug 11, 2010 10:21 am Knockdown and rebuild - building Metr1con Nolan 41 (43) @ http://tim-and-tina.blogspot.com! http://www.verdantdental.com.au Re: How long did your plans take in Council? 16Aug 11, 2010 10:42 am Built the Coral Homes Hamilton 252 - moved in 20/10/2010 and loving it!! https://forum.homeone.com.au/viewtopic.php?t=27215 Re: How long did your plans take in Council? 17Aug 11, 2010 11:54 am ^^ 8 months Funky, passive & enviro = PITA But our shire deals with developers in 5 mins. Where you are coming from is where you are going to... Hi Mofflepop, I would recommend finding a building designer to prepare plans, they should design to your specified budget. The benefit is you can tender the project out… 9 20432 Even if it's not being sub-divided and you want to keep it as Torrens title, you will still need to talk to a town planner or Council themselves, to see if they will allow… 1 11039 We've had the offer of a short term tenant whilst waiting for CDC/DA home approval and demolition for our knock down rebuild. It would achieve a pretty low rent as it's… 0 13759 |