Browse Forums Building A New House Re: DA vs CDC (Approval Times) in Ku-ring-gai Council? 2Feb 13, 2024 4:38 pm minho Hi all, Anyone have experience/knowledge on how long usually either the DA or CDC process it takes for building a new home in the Ku-ring-gai Council area? (Area's such as St Ives, Pymble, Gordon, Kilara)? Thanks in Advance Hi Minho I have heaps of experience in Ku-ring-gai with both DAs and CDC ( this is the main area we build in). DA's are taking 12-18months and CDC's we have been doing in 2-3 months. If you can get your approval via CDC I would highly recommend it. Council is incredibly slow, pedantic and their approval conditions are onerous. All the best Simeon Architectural Homes & Duplexes - specialising in custom designing homes to your budget Get a Free Onsite Consultation Today or send a PM for information, questions or advice. I'm in NSW and am applying CDC for building a retaining wall. The wall only needs to be 800mm at the highest point . I'm thinking just wooden sleepers. 1. For CDC… 0 7912 you need to make an application to your local council for this as they are the approval authority for driveways cheers Simeon 1 15264 It is so easy to do yourself. Even if you are not very handy. You literally only need a few basic things from bunnings. Honestly even with the most basic skills I know… 3 11956 |