Hello Everyone,

Like many before us and more after us, we are have commenced our Rebuild process in NSW. I have spent reading through a lot of blogs in this forum and it has helped me in more than one aspect. As a thank you and in the spirit of sharing my experience with all, I would like to pen my thoughts and updates here.
ITEMFrom DateTo Date
Site Prep and ExcavationThursday, 17 March 202218 March 2022
Pre-pier Inspection (Struc. Consultant and certifier)Saturday, 19 March 202219 March 2022
Pier ConcreteSaturday, 19 March 202219 March 2022
Internal PlumbingTuesday, 22 March 202222 March 2022
Waffle Pod Form and Reinforcement WorksThursday, 24 March 202228 March 2022
Slab Electric ConduitSaturday, 26 March 202226 March 2022
Anti-termite TreatmentSaturday, 26 March 202226 March 2022
Pre-slab Concrete Inspection (Struc. Consultant and certifier)Tuesday, 29 March 202229 March 2022
Slab ConcretingWednesday, 30 March 202230 March 2022
Foundation and Slab CuringThursday, 31 March 20225 April 2022
External Storm Water Drainage PlumbingWednesday, 6 April 20226 April 2022
Storm Water System Inspection (Certifier)Wednesday, 6 April 20226 April 2022
Anti-termite Treatment (Stage 2)Friday, 8 April 20228 April 2022
Timber Frame Works (First Floor Level)Thursday, 14 April 202219 April 2022
Window DeliveryThursday, 14 April 202214 April 2022
Electrical Cable and Meter Box InstallationWednesday, 20 April 202220 April 2022
Rough-ins PlumbingThursday, 21 April 202221 April 2022
Brick Works (Ground Floor)Saturday, 23 April 202226 April 2022
ScaffoldingThursday, 28 April 20222 May 2022
Frame Works for RoofWednesday, 4 May 20226 May 2022
Roof WorksMonday, 9 May 202218 May 2022
Scaffold LoweringFriday, 20 May 202221 May 2022
Brick Works (First Floor)Monday, 23 May 202225 May 2022
Brick CuringThursday, 26 May 202230 May 2022
Brick Washing (First Floor)Tuesday, 31 May 202231 May 2022
Window Glass Supply & InstallationWednesday, 1 June 20221 June 2022
Façade RenderingThursday, 2 June 20224 June 2022
External CladdingThursday, 2 June 20224 June 2022
Roof and Cladding CompletionSaturday, 4 June 20224 June 2022
Eaves InstallationTuesday, 7 June 20228 June 2022
Top Down Pipe InstallationThursday, 9 June 20229 June 2022
Scaffold RemovalFriday, 10 June 202214 June 2022
Façade and Eves PaintingSaturday, 11 June 202214 June 2022
Brick Washing (Ground Floor)Thursday, 16 June 202216 June 2022
Bottom Down PipeFriday, 17 June 202217 June 2022
Lower Level Roof WorksFriday, 17 June 202220 June 2022
Garage Door MeasurementsFriday, 17 June 202217 June 2022
Electrical Rough-ins and AC DuctsSaturday, 18 June 202221 June 2022
Frame Inspection (Certifier & Struc Consultant)Wednesday, 22 June 202222 June 2022
Wall and Roof InstallationSaturday, 25 June 202227 June 2022
Gyprock Including SandingTuesday, 28 June 20225 July 2022
Order Kitchen AppliancesTuesday, 28 June 202228 June 2022
Architrave. Skirting and Door MeasurementsWednesday, 6 July 20226 July 2022
Kitchen & Bathroom ManufacturingWednesday, 6 July 202220 July 2022
Undercoat Painting Tuesday, 7 June 20229 July 2022
Fit-out and Painting CompletionSaturday, 9 July 20229 July 2022
Water ProofingTuesday, 12 July 202213 July 2022
Floor and Wall TilesSaturday, 16 July 202227 July 2022
Order Electrical FixturesFriday, 22 July 202222 July 2022
Garage Door InstallationSaturday, 30 July 202230 July 2022
Staircase InstallationMonday, 1 August 20228 August 2022
Architrave, Skirting and Door InstallationMonday, 1 August 20226 August 2022
Driveway Concreting & CuringMonday, 1 August 20228 August 2022
Installation of Kitchen and Bathroom CabinetsMonday, 8 August 202215 August 2022
Wardrobe & Accessories InstallationMonday, 8 August 202218 August 2022
Electrical Fixtures InstallationMonday, 8 August 202211 August 2022
Fencing & LandscapingTuesday, 9 August 202215 August 2022
Handrails and Shower InstallationTuesday, 9 August 202218 August 2022
Final Coat PaintingWednesday, 10 August 202224 August 2022
Aircon InstallationFriday, 12 August 202213 August 2022
Kitchen Slab and Splashback InstallationTuesday, 16 August 202223 August 2022
Plumbing and Fixtures Finishing WorksTuesday, 16 August 202220 August 2022
Kitchen Appliances InstallationThursday, 25 August 202226 August 2022
Internal CleaningThursday, 25 August 202230 August 2022
Finishing Works - Kitchen and Bath CabinetsSaturday, 27 August 202231 August 2022
Flooring InstallationWednesday, 31 August 20222 September 2022
Skirting InstallationSaturday, 3 September 20225 September 2022
Final Paint Touch-upWednesday, 7 September 202210 September 2022
Silicon SealingMonday, 12 September 202214 September 2022
Final CleaningThursday, 15 September 202216 September 2022
Client WalkthroughMonday, 19 September 202219 September 2022
Occupation Certificate InspectionWednesday, 21 September 202221 September 2022
All the rain and some mess up from the builders side, our build got delayed by months. We are now at the brick work finishing stage. Hopefully, it will be a smooth ride here on out
Related
13/02/2024
1
DA vs CDC (Approval Times) in Ku-ring-gai Council?

Building A New House

Hi Minho I have heaps of experience in Ku-ring-gai with both DAs and CDC ( this is the main area we build in). DA's are taking 12-18months and CDC's we have been doing…

28/09/2023
8
Carlisle KDR site cost after second soil test

Building A New House

We were lucky in that our old house was so small (86 square metres) compared to the new house, they were able to take enough readings around the old backyard house before…

21/09/2023
2
KDR - Home Equity Loan vs Construction Loan

Home Finance

The biggest challenge will be if you take out a loan and then run out of money - you'll have an incomplete security and lenders do not like this so you can get stuck.…

You are here
Building ForumBuilding A New House
Home
Pros
Forum