Browse Forums General Discussion 1 Jul 03, 2018 7:38 pm Hi everyone, We are building the Harmony guest Entertainer and I was wondering if anyone could tell me roughly how long it took to get approval through, we signed off on plans a week ago, we’ve been told it will go through the certifier. Our issue is our pre-approval from the bank runs out in 4 weeks and we would need to re-apply. I’m praying it comes back before then Hi Minho I have heaps of experience in Ku-ring-gai with both DAs and CDC ( this is the main area we build in). DA's are taking 12-18months and CDC's we have been doing… 1 12877 Starting the process to build with Allworth Homes anyone else build the Wyndham four guest 27 or just the Wyndham four 25 or 27 0 5780 you need to make an application to your local council for this as they are the approval authority for driveways cheers Simeon 1 15269 |