was looking over our plans today checking them against the brickwork which is currently being done and noticed that in our laundry we have a gap between the end of the cupboard and brickwork. When the plans were originally drawn the laundry had a glass sliding door which explains why the gap is there. However, we changed this to a single 820mm door with the rest of the area getting bricked up. We are annoyed that we didnt pick this up earlier but wouldnt have thought they would leave a gap between the cupboard and brickwall when we removed the glass slider. We are currently waiting on a reply from the builder.
Do the cupboards and benchtops get made from the original plans or are they made to measure after the brickwork has done? We are hoping the later is the case so nothing has been made yet and we can get it changed so the cupboard runs to the wall without to much of a drama.
Any thoughts? I have attached part of our plan so you can see the gap.