Byford Central-M3 Residential - PCI Defect Remediation
Page 7 of 8
excited much ??
Hahahahaha yeh pretty much LOL!!
Painter doing touch ups today
Fly screens booked for the 10th
Insulation goes in 14th
Render - can't remember the date, this week I think
Handover 15/16th Dec
All other defects are relatively small, and cosmetic.
Very happy.
fantastic job !
Merry Christmas !
House is looking great, love your kitchen, bathroom and flooring! All works very well together
What a quick efficient build
AND the gas isnt connected yet..... just drop that in last minute!!
So Im picking up the keys from their office this arvo, and still moving my stuff tomorrow, but there will be no hot water or stove
I rang Adco myself and they advised that authority for pulling up pavers was given to them 1.5hrs ago... and that it will be connected up to 5 working days from now. And then M3 need to arrange for the plumber to connect the hot water to gas?
FFS!!
I love what you have done so far!
Please can you let me know who the supplier is for your vinyl flooring?
Well I'm moved in, still waiting for gas to be connected.
A few issues I've also picked up since being in the house, nothing too major apart from the garage door has fallen off the frame
Still unpacking, will put up photos when I'm done.
Chrissie tree is up
Flooring is by carpet court in cannington - speak to Frank - by far the best person I have had to deal with through the entire build. Tell him I sent you.
Still sorting PCI defects outs, about half done. Major issues now are with the paving.
Some pics
Fingers crossed the issues get sorted soon, must be frustrating...
Look forward to some more pictures
Brick clean – On front, entrance, alfresco etc needs re-doing - Guys said the chemicals they were using were not working
Drains at front not draining, floods front of property - Maint guys could not do as needs professional
Grout from bath hob to vanity cracking at side of vanity - There is one small area that was not done
Light switch – fan on the top instead of light - Maint guys could not do as hard wired and needs an electrician
IKON glass and they will also be in touch in relation to missing strips at the bottom of the shower screen - DONE
Paving under power box requires reinstatement
Paving Driveway - Sinking RHS Top
Paving Driveway – high lip in a few sections at road
Paving - not level at garage door, doesn't seal
Paving Alfresco – Chips, uneven etc
Paving - Gap at front of house, gap at front door
Paving - Falling apart completely at front
Front archway - gap in gutter showing
Gas system – Large dent in door – door pushed in
Gas BBQ connection - Corroding - 6 month defect
Tile grout not sealed – in all wet areas
Power Points – Light switch still covered in corrosion
Ensuite Light Switch dented
Door - Handle internal corroding - 6 month defect
M3 Residential Sign - To be removed - DONE
Gas cooktop - burner not working - waiting for parts
Oven - touch plate needs replacing - waiting for parts
Waiting on parts, trades etc etc
Related
15/01/2024
7
Its the flashing and is normal. Some builders cover them up others just leave them handing. You can cover it up with an aluminium bracket or ask the builder.
11/07/2023
1
you need to understand the breakdown of warranties. 90 warranty is considered as minor defects rectification period where as the longer ones are more major/structural…
31/01/2024
1
Building Standards; Getting It Right!
There doesn't look to be any rebate in the slab to prevent water from scooting under the window. AS4654 is the Australian standard to look at/refer to. They have…