Posts
ManDam
5 November 2022
10
Nov 05, 2022 12:34 pm
The tap was a 'side' question not related to the flooding. Yes you have a charged rainwater harvesting system. Certainly no possibility of or consideration ever given to utilising that pipe for drainage. Re drainage, you have had an abnormal amount of rain lately. I would concentrate on laying some...
It seems to me that the hydraulics engineer stuffed the design on the left hand side and forgot to provide it. If there...
Read PostLike
ManDam
5 November 2022
8
Nov 05, 2022 11:09 am
Here is the hydraulics showing lines running around the house. Think the pipe on the left is charged. Question is not the tap, we have water logging on the entire left hand side. https://forum.homeone.com.au/u/101514_1667610550.jpg
Here is the hydraulics showing lines running around the house. Think the pipe on the left is charged. Question is not th...
Read PostLike
ManDam
4 November 2022
1
Nov 04, 2022 5:50 pm
Howdy all, Here to ask a question about the drainage on the sides of the house. Builder has provided drainage on one side of the house. We took the pipes provided and converted them into drains. One the narrow side of the house, there is no drainage whatsoever. That is leading to water pooling. I sp...
Howdy all, Here to ask a question about the drainage on the sides of the house. Builder has provided drainage on one sid...
Read PostLike
ManDam
18 October 2022
34
Oct 18, 2022 1:28 pm
Generally it was decent job. We are still settling in so opinions will firm as we go along. The general build quality and finishing is what you would expect. We did inspection at different stages of the house and there were no comments. One of the issues we are facing is drainage at the side of the ...
Generally it was decent job. We are still settling in so opinions will firm as we go along. The general build quality an...
Read PostLike
User avatar  and 1 other person likes this.
ManDam
6 September 2022
32
Sep 06, 2022 9:29 am
So the day is finally close. We are getting the handover for the house on September 9th. We had the practical completion walkthrough and some defects were picked up. Nothing out of the ordinary though. Excited about moving in and finally living here. https://forum.homeone.com.au/u/101514_1662417926....
So the day is finally close. We are getting the handover for the house on September 9th. We had the practical completion...
Read PostLike
ManDam
26 July 2022
31
Jul 26, 2022 11:36 am
So our house is in final finishing stages with carpets being put in and driveway being poured. We are expecting handover in the next 4 weeks. We are trying to schedule some electrical work in our house before handover so that the move in can be smooth. Downlights, ethernet ports, security cameras, s...
So our house is in final finishing stages with carpets being put in and driveway being poured. We are expecting handover...
Read PostLike
ManDam
7 June 2022
30
Jun 07, 2022 4:09 pm
So more progress on the building site. We have the bricks and internals done. The tiling is done as well so we are the final stage now. We had a change of project manager but no impact on build progress. https://forum.homeone.com.au/u/101514_1654582118.jpg
So more progress on the building site. We have the bricks and internals done. The tiling is done as well so we are the f...
Read PostLike
ManDam
5 April 2022
29
Apr 05, 2022 12:27 am
Just a quick update. King homes have been trying to locate brickies but been having trouble doing it. Had a bunch of brickies come by and back away at the last moment. This along with the rain means our project is falling behind. So they are going to do a reverse build doing the internals first and ...
Just a quick update. King homes have been trying to locate brickies but been having trouble doing it. Had a bunch of bri...
Read PostLike
ManDam
4 February 2022
28
Feb 04, 2022 10:34 am
So the framing of the house is done. The next step would be the bricks and tiling. The house is taking shape and a life of its own. King homes have promised to deliver by April so lets see if they live up to their promise. So how is the experience with King so far? Too early to say TBH. Lots of fac...
So how is the experience with King so far? Too early to say TBH. Lots of factors in the mix right now. The framing is f...
Read PostLike
1 person likes this.
ManDam
2 February 2022
26
Feb 02, 2022 9:21 pm
So the framing of the house is done. The next step would be the bricks and tiling. The house is taking shape and a life of its own. King homes have promised to deliver by April so lets see if they live up to their promise. https://forum.homeone.com.au/u/101514_1643800896.jpg https://forum.homeone.co...
So the framing of the house is done. The next step would be the bricks and tiling. The house is taking shape and a life ...
Read PostLike
ManDam
28 November 2021
24
Nov 28, 2021 3:27 pm
So more progress it seems. The slab has been poured. Despite the rains and all, I hope it has been cured. Last week I saw the foam being out in as well. So the pictures are progression from putting foam in to completely covered and poured. https://forum.homeone.com.au/u/101514_1638077214.jpg https:/...
So more progress it seems. The slab has been poured. Despite the rains and all, I hope it has been cured. Last week I sa...
Read PostLike
ManDam
2 November 2021
22
Nov 02, 2021 9:37 am
So after some wait and administrative work, we got our approval from private certifier. A site supervisor has been appointed as well for our project. No contact from him but I expect some feedback soon. A fence has gone up around our property and the slab is supposed to be poured soon. https://forum...
So after some wait and administrative work, we got our approval from private certifier. A site supervisor has been appoi...
Read PostLike
User avatar  likes this
ManDam
21 September 2021
17
Sep 21, 2021 2:56 pm
So a quick update in the house. The house has been pulled down and all asbestos removed from site. The construction is ready to start pending final plans. I have been promised that it should start soon so no more waiting I would think. https://forum.homeone.com.au/u/101514_1632200098.jpg https://for...
So a quick update in the house. The house has been pulled down and all asbestos removed from site. The construction is r...
Read PostLike
ManDam
20 August 2021
12
Aug 20, 2021 10:26 am
we had colours booked in , but days before our meeting NSW lockdown laws kicked in and we have not been able to do this. they are now proposing a virtual colours selection and will not consider any extension to their tender expiry date - which i think is an appalling way to treat your new customers...
When did you sign the contract and when is the tender expiry date? If they cant do tender in person because of the lock...
Read PostLike
ManDam
18 August 2021
9
Aug 18, 2021 10:48 am
@duplex we are looking building a double storey honestly.. i could not fault the initial sales process.. BUT that just gets you to sign their agreement.. they still have yet to build the house. We have not done colours or anything else yet. Since accepting the tender, we have already been affected ...
We are currently building with King homes. Link to build is in sig. How is your internal selection process coming along?
Read PostLike
ManDam
28 July 2021
15
Jul 28, 2021 11:09 pm
lack of communication, believe should be due to lockdown hopefully. I will be watching your posts. Am expected to my private architect's designs in one to two weeks and will send them to King Homes, to see how much they will estimate for cost Im also considering them for a custom build. If you dont...
Im also considering them for a custom build. If you dont mind me asking, which architect company are you using and do t...
Read PostLike
ManDam
23 July 2021
11
Jul 23, 2021 4:58 pm
Another quick update. The lockdown has shifted our plans for demolition. Since construction has been halted, we are now looking at first week of August. In the meantime, we have arranged for the trees to be removed by council. They were quick to withdraw the money so hopefully the removal is just as...
Another quick update. The lockdown has shifted our plans for demolition. Since construction has been halted, we are now ...
Read PostLike
ManDam
23 June 2021
13
Jun 23, 2021 10:54 pm
I am building a 5BR house in Sydney for around that price. We did get lots of upgrades such as 2 master bedrooms, tricked out butler's pantry, big windows etc. One caveat is that we build single storey. Given that Brisbane should be more reasonable than Sydney, I think you could get something at $4...
Hi ManDam, Are you building single story or double storey house?Who are you building with and what size? Thanks Hi Harr...
Read PostLike
ManDam
16 June 2021
10
Jun 16, 2021 10:13 am
So just a quick update. Our papers were put in on 11th June for council approval. Getting the colors and bricks sorted out was quite the journey. Ultimately, wifey and I settled on red bricks from PGH for our house. We are seeing lots of builds with dark colored bricks and wanted something different...
So just a quick update. Our papers were put in on 11th June for council approval. Getting the colors and bricks sorted o...
Read PostLike
ManDam
27 May 2021
8
May 27, 2021 3:50 pm
So far it has been pretty positive. Things are moving and we hope to have council approval quick. Mark runs a tight ship.
So far it has been pretty positive. Things are moving and we hope to have council approval quick. Mark runs a tight ship.
Read PostLike




Australia's largest home building and
renovation community
Homeone
About

Terms
Privacy

Follow homeone on FacebookFollow homeone on Twitter
All comments made express the views and opinions of the author and not the Administrators, Support nor Homeone Australia & New Zealand
© Homeone Australia & New Zealand All Rights Reserved ‎2001 - 2024