Browse Forums Building A New House Re: Who is building with Beechwood 101Feb 24, 2011 5:50 pm Paid deposit-22/3/11 Plans ready and signed off 23/4/11 Plans submitted to Council 23/5/11 Plans received in post 31/5/11 Contracts signed 3/6/11 Ready for slab 8/8/11 Finished and in 19/12/11 Re: Who is building with Beechwood 104Feb 24, 2011 7:16 pm Our Acreage Build The Lakeview Lodge - Beechwood Homes 01/04/10 YES 2010 - Deposit paid 23/09 - PCI CANCELLED 28/09 - PCI - will it happen.-18 months later 07/10/11 - ITS OURS..WOOHOO Re: Who is building with Beechwood 105Feb 24, 2011 8:04 pm just starting Lake View Lodge - Beechwood deposit 17/08/09 Council April 10 signed contract 11/06 earthworks started 9/07 slab completed 8/09/10 Frames 21/09/10 bricking finished 13/10/10 roof 22/10/10 Gyprock 22/11/10 Tiles bathroom 21/12/10 Kitchen in 21/12/10 Painting 09/02/11 handover 11/03/11 We are in 15/03/11!!!!!!!! http://kathdom.blogspot.com/ Re: Who is building with Beechwood 108Feb 25, 2011 5:57 pm Our Acreage Build The Lakeview Lodge - Beechwood Homes 01/04/10 YES 2010 - Deposit paid 23/09 - PCI CANCELLED 28/09 - PCI - will it happen.-18 months later 07/10/11 - ITS OURS..WOOHOO Re: Who is building with Beechwood 110Feb 25, 2011 7:40 pm Paid deposit-22/3/11 Plans ready and signed off 23/4/11 Plans submitted to Council 23/5/11 Plans received in post 31/5/11 Contracts signed 3/6/11 Ready for slab 8/8/11 Finished and in 19/12/11 Re: Who is building with Beechwood 114Feb 28, 2011 6:01 pm Paid deposit-22/3/11 Plans ready and signed off 23/4/11 Plans submitted to Council 23/5/11 Plans received in post 31/5/11 Contracts signed 3/6/11 Ready for slab 8/8/11 Finished and in 19/12/11 Re: Who is building with Beechwood 115Feb 28, 2011 6:18 pm Our Acreage Build The Lakeview Lodge - Beechwood Homes 01/04/10 YES 2010 - Deposit paid 23/09 - PCI CANCELLED 28/09 - PCI - will it happen.-18 months later 07/10/11 - ITS OURS..WOOHOO Re: Who is building with Beechwood 117Feb 28, 2011 8:25 pm McKeachies Run, Aberglasslyn Deposit paid 11th April Land registered 6th June Land settled 20th June Colour selections and contract signed 5th August Commencement letter received 26th September Re: Who is building with Beechwood 118Mar 01, 2011 9:06 am just starting Lake View Lodge - Beechwood deposit 17/08/09 Council April 10 signed contract 11/06 earthworks started 9/07 slab completed 8/09/10 Frames 21/09/10 bricking finished 13/10/10 roof 22/10/10 Gyprock 22/11/10 Tiles bathroom 21/12/10 Kitchen in 21/12/10 Painting 09/02/11 handover 11/03/11 We are in 15/03/11!!!!!!!! http://kathdom.blogspot.com/ Re: Who is building with Beechwood 119Mar 01, 2011 9:38 am Our Acreage Build The Lakeview Lodge - Beechwood Homes 01/04/10 YES 2010 - Deposit paid 23/09 - PCI CANCELLED 28/09 - PCI - will it happen.-18 months later 07/10/11 - ITS OURS..WOOHOO Re: Who is building with Beechwood 120Mar 01, 2011 9:51 am We haven't got a home phone so we didn't get the cables laid. We were going to but they dug and laid the electricity cable in about 4 hours and didn't tell us what day they were going to do it. So we have no home phone or even the cables to connect the phone. If you want it done you need to organise for a telstra contractor to come and connect while the trench is open.....good luck with that. just starting Lake View Lodge - Beechwood deposit 17/08/09 Council April 10 signed contract 11/06 earthworks started 9/07 slab completed 8/09/10 Frames 21/09/10 bricking finished 13/10/10 roof 22/10/10 Gyprock 22/11/10 Tiles bathroom 21/12/10 Kitchen in 21/12/10 Painting 09/02/11 handover 11/03/11 We are in 15/03/11!!!!!!!! http://kathdom.blogspot.com/ Hey guys building a new place through a volume builder and just wondering if i should complain to the site supervisor as we just had plasterboard installed. Looks like… 0 11853 Elvis has left the building... The site supervisor quit after 2 month on the project. I guess he was just instructed to bark at people, but didn't like when he was… 26 21656 |