I've been following along with lots of builds in the Clarendon thread, and thought, seeing as we're finally making some progress, that I'd start my own thread.
We're building the Armadale 37 - floor plan in following post -with Clarendon.
Timeline:
- April 2015: Settled on 450sqm block in an established area of NW Brisbane
- June 2015: Signed contract with Clarendon
- 7 September 2015 - build week 1: Site works commenced (after some back and forth on retaining walls and drop edge beams)
- 14 September 2015: we built a retaining wall, before works could continue
- 17 - 29 September 2015: plumbing etc, through to slab completion
- 6 October 2015: frame started
- 17 October 2015: fascia and gutter started
- 20 October 2015: upper roof on
- 29 October 2015: lower roof on (with a hole, due to steel beam in garage being too long
![Shocked :shock:](./images/smilies/icon_eek.gif)
- 6 November 2015: windows FINALLY delivered and installed the next day
- 17 November 2015: bricks had started earlier in the week - realised part of the front facade was wrong (resolved very quickly, thankfully!)
- Nothing, other than bricks, happened for like a month!
- Christmas/New Year period: gyprock installed
- 18 January 2016 - build week 21: Cladding and eaves installed; plastering done; stairs delivered