I told you that. They were doing final marking yesterday and said they will start tomorrow. But not sure whether they will or not. Lets see. Will update on Monday.
Oh do they work on Saturdays?
viewtopic.php?t=86597
Think so as they did our slab on Saturday morning. They took about 4-5 days after clearing the land. After clearing they did pipe work and took a while after that to do the slab. Almost about 2-3 weeks after the piping work. I am saying because when I left for overseas they did the digging after 1-2 days and then they put the pipes and after that they took 2-3 weeks to put the slab. They did our slab on 1st July.