Congrats on finally getting in, I actually lost your thread. Happy if you message me directly instead. How many days were you finally overdue? How was the compensation process? I am still a while away from walk through and handover. Any tips on what can be done to speed up the process?
Thanks Nev. Our liquidated damages amounted to 5 months @$30/day.
Best not to rush the build as there will be more errors. Try to get everything completed before PCI so handover can be quicker and smoother. We have some items outstanding even after handover and it's now about scheduling someone to be home to allow access which can delay works. Your build is powering along very quickly.