Just wondering if anyone has had a situation in their PCI that the lights/powerpoints were switched off?
We had ours last week and the electricians were coming back to instal one more downlights due to a roof timber in the way. Our SS asked them to wait till after PCI because we may have needed them to come back to fix other items anyway and it allowed them to get it all done at once(we had pendents and there were a few issues)
We wernt able to test anything but our SS assured us they can't handover unless the electricians have tested and signed off on everything anyway- i do trust them that it will all be functional but I'm wondering if it was silly of me to take their word for it?
Also how picky exactly can you be? There were things I mentioned that my SS stated were not fixable and just the way they are which I have accepted..
For example the ceiling sheets in the garage come a little short and there is a small hole between brickwork and the edge of the ceiling