Remember Androolz - they did not fix his pre-pour slab rectifications - and later had to drill into the slab to fix - ask for photos of rectification - the soil test for my site has been ordered - so lets how soon we go to site as well
Yeah, I've read through Androolz troubles, it's the main reason why I've engaged an independent inspector.
I've texted my SS and told him I want to be on site to make a visual inspections of the rectified works myself before they pour the concrete tomorrow.
We too got one after reading his blog. Our SS was good and took the report seriously and rectified. Now mid build our SS has changed, and the new one has been dismissive of independent inspectors in general. This a big red flag for me. Now we are stressed.
I think we all who are about to build would want to know the SS who is dismissive of independent inspector - After all Arden probably needs clients more than a SS. Such SS must be reported to management. It's only when we all who build will lodge a complaint Arden would notice.