Browse Forums Building A New House 1 Jul 24, 2010 10:10 pm We are building with *! - Gone for the Grandview, building in Jindalee, all going well just had planning approval this week. Been told 3 weeks to slab down. Anyone else think that build times have speeded up? Paid $2000 deposit 25-05-10 Received contract & drawings 11-06-10 Pre-start 30-06-10 Building approval 21-07-10 Slab down w/e 23-08-10 Window frames delivered 26-08-10 Brickwork started 08-09-10 Brickwork complete 21-09-10 Roof started 02-10-10 Roof timber complete 15-10-10 First fix plumbing complete 18-10-10 First fix wiring completed 21-10-10 Roof tiling started 22-10-10 Re: Building thread - * 3Aug 03, 2010 9:34 pm yes its moving on, at a good rate, the land has been levelled now, waiting for the earth works to start next week. Paid $2000 deposit 25-05-10 Received contract & drawings 11-06-10 Pre-start 30-06-10 Building approval 21-07-10 Slab down w/e 23-08-10 Window frames delivered 26-08-10 Brickwork started 08-09-10 Brickwork complete 21-09-10 Roof started 02-10-10 Roof timber complete 15-10-10 First fix plumbing complete 18-10-10 First fix wiring completed 21-10-10 Roof tiling started 22-10-10 Re: Building thread - * 4Aug 07, 2010 3:30 am We are in Jindalee and the houses certainly seem to be flying up. There was a problem a while back with trades but I am not so sure now. Re: Building thread - * 5Aug 07, 2010 6:32 am We have found once you get to on site things just take off - faster than u think. Good luck! Jazz and Brett 18m Q2 Retr3@t {Cremorne Facade} Pl@nt@t10n H0m3s {Underwood, QLD} The House that Jazz and Brett Built Blog http://jazzandbrett.blogspot.com/ Build Thread: https://forum.homeone.com.au/viewtopic.php?f=31&t=35491 Re: Building thread - *! 6Aug 23, 2010 4:54 pm Slab down today, looks massive. Anyone know how long they leave slab before they start the brickwork? Paid $2000 deposit 25-05-10 Received contract & drawings 11-06-10 Pre-start 30-06-10 Building approval 21-07-10 Slab down w/e 23-08-10 Window frames delivered 26-08-10 Brickwork started 08-09-10 Brickwork complete 21-09-10 Roof started 02-10-10 Roof timber complete 15-10-10 First fix plumbing complete 18-10-10 First fix wiring completed 21-10-10 Roof tiling started 22-10-10 Re: Building thread - *! 7Aug 23, 2010 5:14 pm Congrats on your slab! It's so exciting when things start to happen!! It was 10 days from our slab until they started the frame. MM Building Doulton Q3 with Plantation Homes My Building Blog http://thewebbs-page.blogspot.com/ Building Thread https://forum.homeone.com.au/viewtopic.php?f=31&t=32743 Re: Building thread - *! 8Sep 22, 2010 4:20 pm It's a small world. We built with * in Jindalee (Jindalee Boulevard) and have been in our house for 4 months. They were very fast to lock up stage but then it took another 4 months until we got the keys, so I hope for your sake they have sorted out the delays after lock up. Jindalee is a great place to live and the land is such good value compared to Burns Beach etc. But we better no tell anyone or the secret may get out!! Re: Building thread - *! 9Oct 25, 2010 11:21 pm Just about to sign on with this builder.. keen to hear feedback, pos or neg is appreciated. L Building the 'Grandview' in Meve, WA land deposit paid 10/10 Hi, Apologies - I know there is plenty out there on this but struggling to put together the puzzle. We're planning our garage/external laundry to master bedroom and… 0 10925 Thanks for your reply. I will just wait and see I guess. Trying to get some more information from our builder. 9 30233 |