Deposit 5% (you have already payed 1500 initial deposit and 3000 contract deposit and so this is minused from this amount. This balance is due after you sign the contract document. )
Base stage 10%
Frame Stage 15%
Lockup stage 35%
Fixing stage 25%
Completion 10%
Carlisle tried to change the payment schedule on us so double check this part of your contract. They cant change it unless you agree that your house is unusual in some way that you agree different progress payment percentaged are necessary... dont let them pressure you here. They arent allowed to go against what is stated in the hia contract as standard. They addressed this for us in the post contract variation.
Anyways, ive got to go to work now. Ill add more soon.
Hi Orange
Thanks for the advice
BTW , we might build the same house with same facade (according to your pic)