Browse Forums Building A New House Re: Porter Davis homes 6978Apr 02, 2013 12:02 pm To anyone thinking of building with Porter Davis My son and i are building the Waldorf 48 House and Land Package The Process started in October 2012 ... We choose the Waldorf 48 for the great floor plan and wanted the house and land package thinking there would be no surprises with site costs or planning and building permits ...Be aware of all the costs before signing the contracts... When buying a house and land Package we didn't realize that there where so many problems 1. You have to purchase the land before you have the contract appointment where you find out all the extra hidden costs that nobody can/will tell you about. 2.Planning problems that delays the site start Told that our site start would be at the end of March early April 2013 at contract appointment 22 Feb.... ............ <quote edited and reduced by kexkez Support Member. > These are just a few of the problems we have had so far there have been many more to many to mention ...I will continue to post updates until the build is finished ...if it ever gets started Re: Porter Davis homes 6979Apr 02, 2013 12:04 pm Quote: I notice you removed the alifrost doors and got a credit. Did you remove the doors completely or just change the doors to laminex? I've been told I need to pay to switch from alifrost to laminex, even though I have paid for the upgrade to alifrost doors in a package! Confusing! I think as we have all learnt from this site, there is not consistent quoting or pricing with PD, everyone seems to have something different, depends on who you speak to on which day and which office. Pick your battles. There are some things the SC said we would be credited for, but when questioned at Tender, the answer was no. We deleted the Alifrost and my understanding is they are replaced with laminex, better double check that! So a win for us on this one, but there were other battles we lost. Re: Porter Davis homes 6980Apr 02, 2013 1:01 pm MummaDJ Quote: I notice you removed the alifrost doors and got a credit. Did you remove the doors completely or just change the doors to laminex? I've been told I need to pay to switch from alifrost to laminex, even though I have paid for the upgrade to alifrost doors in a package! Confusing! I think as we have all learnt from this site, there is not consistent quoting or pricing with PD, everyone seems to have something different, depends on who you speak to on which day and which office. Pick your battles. There are some things the SC said we would be credited for, but when questioned at Tender, the answer was no. We deleted the Alifrost and my understanding is they are replaced with laminex, better double check that! So a win for us on this one, but there were other battles we lost. Thanks, I will double check that Three options 1 Ask the liquidator 2 Find another PD customer and ask the source of their report 3 Pay for new report 3 12337 Ask for references and speak to them. If they are defensive or try to avoid the request, walk. 1 74701 I would never build with Fowler homes. I built with them in 2021 and till date maintenance issues are pending. All their existing trades and businesses don't work with… 14 105553 |