Browse Forums Building A New House Re: Porter Davis homes 6739Feb 27, 2013 9:30 pm they will only listen to their inspectors reports. per building regs the stages which must be approved are: pre-slab slab framing compliance at the end, roof plumbing, plumbing, electrical, water proofing and energy rating. the rest are the other inspections are irrelevant to builders (pre-plaster, fixing, PCI), actually not required. As a customer you need to ensure that work is per the regs and 2007 standards & tolerance. Three options 1 Ask the liquidator 2 Find another PD customer and ask the source of their report 3 Pay for new report 3 12332 Ask for references and speak to them. If they are defensive or try to avoid the request, walk. 1 74700 I would never build with Fowler homes. I built with them in 2021 and till date maintenance issues are pending. All their existing trades and businesses don't work with… 14 105532 |