Hello all, I thought I would join in with everyone else and start my own thread about our upcoming build. We have been looking primarily at building with Celebration at this time but we are just waiting for a meeting on the coming Friday to see how things price up and look to make our decision. I will try and keep this post up to date with the latest details as my fiance and I are super excited.
TIMELINE
===================
Pre-Approval: 5th November, 2012
Land Deposit: 10th November, 2012
House Deposit: 28th November, 2012
Contracts Received: 5th April, 2013
Contracts Signed: 30th April, 2013
Prestart Completed: 14th May, 2013
Titles Issued: May 28th, 2013
Finance Approval: 4th June, 2013
Settlement Date: 20th June, 2013
Site Scraped: 19th July, 2013
Slabbed: 23rd July, 2013
Bricks and Frames Delivered: 10th August, 2013
Brickwork Started: 21st August, 2013
Brickwork Finished: 17th September, 2013
Roof Frame Done: 27th September, 2013
Eaves and Gutters Done: 1st October, 2013
Roof Tiles Started: 10th October, 2013
Roof Completed: 15th October, 2013
Grey Float Started: 15th October, 2013
Grey Float Finished: 17th October, 2013
Windows and Sliding Doors Installed: 18th October, 2013
White Set Started: 19th October, 2013
White Set Finished: 22nd October, 2013
Ceilings Started: 25th October, 2013
Ceiling and Cornice Finished: 30th October, 2013
Lock-up: 5th November, 2013
Roof Tile Edges Completed: 6th November, 2013
Ceiling and Cornice Painted: 6th November, 2013
Internal Doors Painted and Fitted: 7th November, 2013
Cupboards and Benchtop Installed: 8th November, 2013
Bathroom and Laundry Sinks Installed: 8th November, 2013
Front Grey Float Applied: 9th November, 2013
Taps, Bath, Water Connections Finished: 13th November, 2013
Tiler Started: 13th November, 2013
Tiler Finished: 18th November, 2013
Garage Floor Laid: 19th November, 2013
Lock-up Meeting Onsite: 20th November, 2013
PCI/Pre-Handover: 6th December, 2013
Key Handover: 20th December, 2013
===================