After posting so many comments in Balmoral rd Release thread, I finally decided to have my own thread....(Yes, T, gogo...
![Laugh ::lol::](./images/smilies/Laugh.png)
My husband & I decided to buy a land in June 2009 and we chosed an unregistered land in Kellyville, NSW.
After waiting for soooo..long, the land finally registered in November 2011. Yes, more than 2 years....
![Angry ::angry::](./images/smilies/Angry.png)
Long story short, we finally decided to choose Wisdom homes for our house. It's called Boston 48, but we changed the layout so many times that now I think looks similar to Wisdom's design called Manhattan...
![Laugh ::lol::](./images/smilies/Laugh.png)
We added 3rd garage and make the whole house brick face , and now becomes Boston 50.7sq.
The timelines are below :
June 2009 : Deposit 5% for land
Nov 2009 : Deposit $600 to Wisdom homes
06 Oct 2011 : Contract's signed
Nov 2011 : land is registered
25 Nov 2011 : DA Approved (3 weeks only)
20 Feb 2012 : Site Cut
13 March 2012 : Piering
17 March 2012 : Slab's done
5 April 2012 : Frames & Windows finished
And here some photos of the house :
http://i1220.photobucket.com/albums/dd444/willcress/056.jpg
http://i1220.photobucket.com/albums/dd444/willcress/052.jpg
http://i1220.photobucket.com/albums/dd444/willcress/041.jpg
http://i1220.photobucket.com/albums/dd444/willcress/048.jpg
Cheers...