Browse Forums Building A New House Re: Porter Davis homes 4003Dec 13, 2011 9:07 am Porter Davis Homes Questions? Call 1800PORTER Mon - Fri 9am-8pm Sat - Sun 10am-4pm info@porterdavis.com.au http://blog.porterdavis.com.au/ http://www.porterdavishomes.com.au Re: Porter Davis homes 4005Dec 13, 2011 11:27 am Cheers, Alpal Building PD Heathmont 40 BLOG: http://alpal-pd-heathmont40.blogspot.com/ Deposit paid 19/08/2011 Contract signing 3/10/2011 Site Start 10/11/2011 Slab 23/11/2011 Re: Porter Davis homes 4006Dec 13, 2011 11:32 am Cheers, Alpal Building PD Heathmont 40 BLOG: http://alpal-pd-heathmont40.blogspot.com/ Deposit paid 19/08/2011 Contract signing 3/10/2011 Site Start 10/11/2011 Slab 23/11/2011 Re: Porter Davis homes 4007Dec 13, 2011 12:36 pm Forrestdale 27 Land Titled:4/11/11 Building Permit:4/11/11 Site Start Date: 16/11/11 Slab Date: 01/12/11 Frame Date:05/12/11 http://hordefamilyhome.blogspot.com/ Porter Davis homes 4008Dec 13, 2011 2:13 pm Building the Drysdale 30 Wallara Waters, Wallan My Blog : http://www.ourwallanhome.blogspot.com My thread: https://forum.homeone.com.au/viewtopic.php?f=31&t=50975 Re: Porter Davis homes 4009Dec 13, 2011 2:37 pm Hi Cattycatcat, I would probably raise it with the SS because the last thing you want is to be able to see the scratches or bend once it is installed. Isnt it awesome to hear how everyones homes are progressing....i check every night or during the day and someone alaways has some to share. Keep us posted on what you decide to do. Forrestdale 27 Land Titled:4/11/11 Building Permit:4/11/11 Site Start Date: 16/11/11 Slab Date: 01/12/11 Frame Date:05/12/11 http://hordefamilyhome.blogspot.com/ Re: Porter Davis homes 4010Dec 13, 2011 3:22 pm cattycatcat We have 3 glass sliding doors, on one of the doors at the top the metal has been bent out of shape and some of the paint has been scratched off. This isn't a structural issue, it's purely aesthetic. Should I bring it up with my SS next time he calls me or should I just let it go and live with it? Thanks in advance Bring it up, we had the same issue, and they swapped it out.. it would be covered during the PCI anyways. Re: Porter Davis homes 4011Dec 13, 2011 5:53 pm Handover is booked for the 20th of December (next week... yahhhhh). Our SS you have done a fantastic job on the house. It's a pain in the backside organising all the connections..... Telstra, Electricity & Gas. Porter Davis homes 4012Dec 13, 2011 7:50 pm tstr1a Handover is booked for the 20th of December (next week... yahhhhh). Our SS you have done a fantastic job on the house. It's a pain in the backside organising all the connections..... Telstra, Electricity & Gas. That's awesome news! How many days for your build does that make? Seems amazingly fast for such a bit house Porter Davis homes 4013Dec 13, 2011 9:28 pm Congrats T! That is wonderful news... Merry Christmas to you and your wife indeed!!! Much work to do following PCI? Re: Porter Davis homes 4014Dec 13, 2011 9:32 pm That's awesome news tstr1a ! The place looks amazing! Cant wait to see more pics once you have moved in your personal touches Forrestdale 27 Land Titled:4/11/11 Building Permit:4/11/11 Site Start Date: 16/11/11 Slab Date: 01/12/11 Frame Date:05/12/11 http://hordefamilyhome.blogspot.com/ Re: Porter Davis homes 4015Dec 14, 2011 8:21 am Wateman tstr1a Handover is booked for the 20th of December (next week... yahhhhh). Our SS you have done a fantastic job on the house. It's a pain in the backside organising all the connections..... Telstra, Electricity & Gas. That's awesome news! How many days for your build does that make? Seems amazingly fast for such a bit house Thanks waterman, the house has taken 156 days to build which I think is amazing. My SS hasn't pushed the build either, we were lucky to have good weather from July to Sept and most importantly that all tradies turned up before schedule. Major hold ups happen at the bricking, painting and tiling stages. Here you can lose a month + if there is delays. Re: Porter Davis homes 4016Dec 14, 2011 10:22 am Hi All, Quick question.... Has anyone run their own cabling during the building works? I would like to run some CAT6 cable to 3-4 rooms and was wondering if anyone has done this and PD were OK with it... Also when is the best time to do this - I am suspecting just before plastering Any feedback would be great Cheers, Alpal Building PD Heathmont 40 BLOG: http://alpal-pd-heathmont40.blogspot.com/ Deposit paid 19/08/2011 Contract signing 3/10/2011 Site Start 10/11/2011 Slab 23/11/2011 Re: Porter Davis homes 4018Dec 14, 2011 10:42 am Hi All, for those of you wanting a PCI checklist here is a great site I found thru this forum. http://www.anewhouse.com.au/?p=296 Ivanhoe 36 Dep:18-4-11 Tender:26-5-11 Colour/Electrical:8-6-11 Contract:29-6-11 Building Permit:6-7-11 Site Start:16-8-11 PCI:10-1-12 Handover:24-1-12 http://eli-kay-ivanhoe36.blogspot.com/ Re: Porter Davis homes 4019Dec 14, 2011 11:08 am cattycatcat Wooow... All this progress in such a short amount of time. I love catching up on everyone else's build and reading all your comments.. How did people even build a house before Homeone? Hehe. So any who I actually have a question.. My MIL was checking out the photos we took at the house over the weekend and noticed something we didn't.. We have 3 glass sliding doors, on one of the doors at the top the metal has been bent out of shape and some of the paint has been scratched off. This isn't a structural issue, it's purely aesthetic. Should I bring it up with my SS next time he calls me or should I just let it go and live with it? Thanks in advance Hi Cattycatcat, I love reading everyone’s updates too and being able to offer assistance where I can. I agree with Sammyjane31, I think it’s best to bring everything up with your SS, even some of the minor things. If it isn’t something they would fix, I’m sure they would be the best person to give you some DIY tips on it. Let us know how you go. Cheers, Ebony Porter Davis Homes Questions? Call 1800PORTER Mon - Fri 9am-8pm Sat - Sun 10am-4pm info@porterdavis.com.au http://blog.porterdavis.com.au/ http://www.porterdavishomes.com.au Re: Porter Davis homes 4020Dec 14, 2011 11:16 am tstr1a Handover is booked for the 20th of December (next week... yahhhhh). Our SS you have done a fantastic job on the house. It's a pain in the backside organising all the connections..... Telstra, Electricity & Gas. Hi tstr1a, I’m really pleased to hear that handover has been booked for next week and that your SS has done an amazing job. Good luck with connecting your utilities! I can’t wait to see some more photos. Cheers, Ebony Porter Davis Homes Questions? Call 1800PORTER Mon - Fri 9am-8pm Sat - Sun 10am-4pm info@porterdavis.com.au http://blog.porterdavis.com.au/ http://www.porterdavishomes.com.au Wow that is terrible about the insurance! I guess ideally proof of insurance should be provided prior to first deposit but I'd imagine they would refuse to be out of… 17 14222 There isn't any need to. As I wrote previously, there isn't a set term, there is just commencement based on earlier of contract signing or building permit issue and… 24 13375 Three options 1 Ask the liquidator 2 Find another PD customer and ask the source of their report 3 Pay for new report 3 6489 |