Hi Everyone! I'm a 6month old stalker who has now decided to start a new thread...hope I'm doing it right...
We are building in The Summit @ mt Barker. It is our 2nd build - the first was 9 years ago, and things sure have changed - especially the prices! I will post our plans soon.
We have just begun siteworks and our trenches are being done as I type - huzzah!
Will post more details when I have time to work it all out!
Slab 3/6/11
Frame completed 28/6/11
Windows/doors installed 29/6/11
Bricking started 29/6/11
1st fix electrical 1/7/11
roof on 14/7
gyprock complete 22/7
tiling complete 2/9/10
kitchen and cabinets
Bullnose on 20/8
Stormwater complete 24/8