Time to launch my thread. Table of significant photos below.
The Slab April 11
The FrameApril 21
The Roof April 29
Bricking May 3rd through 28th
Rough ins and Insulation May 22nd
PlasterMay 24th
Lockout May 27th
Fix Out June 8th
PCI July 15th
Moved in August 3rd
Lets get straight into the plans.
Plan: Brando 32 by Bentley
Colours: Yes we like greens and browns. We are boring.
Bricks: Urban One Latte
Roof Tiles: Magnum
Windows: Woodland Grey
Fascia: Jasper
Garage: Loft
Driveway: Brazil Nut
Internal Walls: Cargo River
Kitchen: Burnished Wood with Zulu stone benchtop and Gloss Green Tea splash
Bathrooms (Original selection discontinued): Avignon Walnut or Peruvian Clay with Lunar Stone countertops
Tiles throughout: Loft Olive
Carpets: Dark Stone Cut Pile Plush
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Site Start Date: March 30th 2011
Mow it:
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Scrape it:
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Dig it:
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Plumb it:
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
Waffle it:
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
And hopefully the rain will stay away so next week we can pour it!