duke - I knew that Lis is slightly ahead of me... my concern is that they've only installed the water filter today - can't see anything else...
I should know by the end of this week when my PCI is going to happen.
Browse Forums Building A New House Re: Lis’ Santorini – DAH - We're almost there!!! 181Jan 24, 2011 11:06 pm Preliminary agreement 23/11 Contract 22/03 Prestart 06/04 - finalised on 30/04 Unconditional approval 10/05 Demolition 05/07 Slab 26/08 Brickwork 13/09-06/10 Roof frame started 07/10 viewtopic.php?f=31&t=32292 Re: Lis’ Santorini – DAH - We're almost there!!! 184Feb 02, 2011 10:04 pm Preliminary agreement 23/11 Contract 22/03 Prestart 06/04 - finalised on 30/04 Unconditional approval 10/05 Demolition 05/07 Slab 26/08 Brickwork 13/09-06/10 Roof frame started 07/10 viewtopic.php?f=31&t=32292 Re: Lis’ Santorini – DAH - We're almost there!!! 187Feb 13, 2011 8:59 am Preliminary agreement 23/11 Contract 22/03 Prestart 06/04 - finalised on 30/04 Unconditional approval 10/05 Demolition 05/07 Slab 26/08 Brickwork 13/09-06/10 Roof frame started 07/10 viewtopic.php?f=31&t=32292 Re: Lis’ Santorini – DAH - We're almost there!!! 188Feb 13, 2011 1:31 pm Built with Sw1tch H0mes >Build thread< House status 15/12: Gates and A/C finally installed! Sep 09 Bought block, Dec 09 Engaged builder, Jul '11 Moved in Re: Lis’ Santorini – DAH - We're almost there!!! 191Feb 16, 2011 11:07 pm Preliminary agreement 23/11 Contract 22/03 Prestart 06/04 - finalised on 30/04 Unconditional approval 10/05 Demolition 05/07 Slab 26/08 Brickwork 13/09-06/10 Roof frame started 07/10 viewtopic.php?f=31&t=32292 Re: Lis’ Santorini – DAH - We're almost there!!! 192Mar 14, 2011 2:34 pm Preliminary agreement 23/11 Contract 22/03 Prestart 06/04 - finalised on 30/04 Unconditional approval 10/05 Demolition 05/07 Slab 26/08 Brickwork 13/09-06/10 Roof frame started 07/10 viewtopic.php?f=31&t=32292 Re: Lis’ Santorini – DAH - Got keys, but still so much to do 194Mar 16, 2011 9:44 pm Congrats Lis. Hope the things get sorted out soon. Re: Lis’ Santorini – DAH - Got keys, but still so much to do 195Mar 16, 2011 11:21 pm With similar wise words from Bags... Photos please... Especially the liquid limestone job. Re: Lis’ Santorini – DAH - Got keys, but still so much to do 196Mar 17, 2011 12:59 pm You are so lucky Lis - we had to move out of our rental on the hottest day of Feb had to drop everything in the living/dining area and wherever we found a bare spot as we didn't have the garage door installed at handover. Then the following week when the garage door was finally installed we had to move evertying in the garage. At leaset we are able to move around the house.. I can't take time off work - I'm a contractor so if I don't work I don't get paid - as a result I have to do my painting at night after work or in the weekends... I currently live in 3 tops (t-shirts) and 2 pairs of pants... everything else is tucked away as the dust is so bad... Waiting for the bank to release the funds and the shire to issue the building licence for our retaining so we get some privacy... at the moment I have no fencing around - lucky I bought those Blinds in a Box - they are brilliant.... I should've bought a few longer but I managed to put DAH's old signs at the bottom of the longer windows to achieve privacy... I'm hoping that in 3 weeks I can walk around the house without shoes... Preliminary agreement 23/11 Contract 22/03 Prestart 06/04 - finalised on 30/04 Unconditional approval 10/05 Demolition 05/07 Slab 26/08 Brickwork 13/09-06/10 Roof frame started 07/10 viewtopic.php?f=31&t=32292 Re: Lis’ Santorini – DAH - Got keys, but still so much to do 197May 01, 2011 10:37 am Hi Lis! Glad to hear your journey is almost at an end. We've been admiring your house on our walks, it looks fantastic. I know what you mean about just wanting it to be over! It'll be all yours soon, safe and snug for winter Have you seen the new nature area near the open field? Nice little spot to take a wander. We've got 2 ha of public parkland going in across the estate on the other side of the major road too as part of a new development going up there. Re: Lis’ Santorini – DAH - Got keys, but still so much to do 198May 21, 2011 10:40 am Thanks V! Ooh didn’t know about the public parkland happening across the road. Sounds like a good spot to take the fur-kid for his walkies We’re slowly getting there, had a few hold ups that have prevented us from moving in. We were really hoping to be in by April, but now it looks like June And just to add to the list of things to worry about and plan, we’ve found out that there will be an addition to our family making his/her arrival in September Must really get on to planting that money tree in the backyard - with a new house and baby stuff to buy funds are going to be pretty low House progress so far is that the painting has been done, flooring installed, light fittings are in, glass splashback installed, wardrobe and laundry fit-out done and blinds are due to go in on Tuesday. The main thing that has prevented us from moving in is not having our liquid limestone driveway poured and the paths around the house. All I can say to anyone thinking about getting liquid limestone or poured aggregate is do NOT go with Solution Liquid Limestone. This company has been nothing but a giant PITA! After paying our booking deposit way back in March, and after weeks and weeks and WEEKS of waiting, broken promises and complete lack of communications (from the managing director!) we told them to give us our deposit back and that we’ll be taking our business elsewhere! We lost almost 2 months waiting for them to get their act together but now I’m making it my mission to tell anyone and everyone not to go with this unprofessional and incompetent company! *Rant over* Anyway, we’ve booked with a new company who is due to start work on our place today – Stay tuned… Re: Lis’ Santorini – DAH - Got keys, but still so much to do 199May 21, 2011 10:54 am Jeebies Lis! You should be warm and cozy in your new house by now! Those Solution Liquid Limestone guys need a whip cracked over them, get a wriggle on you slowbos On the bright side, that's awesome to hear about all the little things getting put in. How does the spashback look? And on the brighter, bright side... we're expecting the first Little Vundaful in November so high five to us mamas Re: Lis’ Santorini – DAH - Got keys, but still so much to do 200May 21, 2011 11:02 am Congratulations on the new baby! but grr to 2 months wasted time! And, you know you can't say you've done all that stuff and not show pics!! my new build thread- Ben Trager https://forum.homeone.com.au/viewtopic.php?f=31&t=89826 my switch build thread (2011) https://forum.homeone.com.au/viewtopic.php?f=31&t=36569 Joe, it depends on your certifier but we are noticing the ones we deal with are really cracking down. So i would recommend you follow your approved landscaping plans to… 4 10848 Hi Simeon, Thank you for laying it down for us. Makes sense. Appreciate it very much. Have a nice day. Cheers 2 8888 |