Browse Forums Building A New House Re: Our custom build in the Barossa - getting closer 81Feb 07, 2011 9:09 pm Contracts signed Dec 09 OK to Start Sep 17 Slab Oct 6 Frame Oct 25,26 Windows and Gutters Oct 28 Bricks Nov 2 -20 Roof Finished Nov 10 Insulation and Gyprock Finished Nov 30 Locked Out Dec 13 Cupboards Installed Dec 17 Tile prep work Dec 26 Painter started Dec 30 Stormwater Jan 17 Tiles Jan 10-19 PCI Feb 2 Handover Feb 9 viewtopic.php?f=31&t=37120[size=85] Re: Our custom build in the Barossa - getting closer 82Feb 10, 2011 9:30 pm https://forum.homeone.com.au/viewtopic.php?f=31&t=43937&start=0 Bought a block in Golden Grove - Jan 2011 Finally finished our design, Mar 2012, *yay* Signed with ADH council consent June 12 Re: Our custom build in the Barossa - getting closer 83Feb 10, 2011 10:06 pm Rebecca Custom Build with Kersbrook Constructions - SA https://forum.homeone.com.au/viewtopic.php?f=31&t=37762 Current Status: Handover on Thursday!!!!!!!!!!!!!!!!! Re: Our custom build in the Barossa - getting closer 84Feb 11, 2011 8:49 am https://forum.homeone.com.au/viewtopic.php?f=31&t=43937&start=0 Bought a block in Golden Grove - Jan 2011 Finally finished our design, Mar 2012, *yay* Signed with ADH council consent June 12 Re: Our custom build in the Barossa - getting closer 85Feb 11, 2011 1:21 pm Rebecca Custom Build with Kersbrook Constructions - SA https://forum.homeone.com.au/viewtopic.php?f=31&t=37762 Current Status: Handover on Thursday!!!!!!!!!!!!!!!!! Re: Our custom build in the Barossa - getting closer 86Feb 11, 2011 3:37 pm Rebecca Custom Build with Kersbrook Constructions - SA https://forum.homeone.com.au/viewtopic.php?f=31&t=37762 Current Status: Handover on Thursday!!!!!!!!!!!!!!!!! Re: Our custom build in the Barossa - getting closer 87Feb 12, 2011 9:23 am https://forum.homeone.com.au/viewtopic.php?f=31&t=43937&start=0 Bought a block in Golden Grove - Jan 2011 Finally finished our design, Mar 2012, *yay* Signed with ADH council consent June 12 Re: Our custom build in the Barossa - getting closer 89Feb 15, 2011 5:08 pm Rebecca Custom Build with Kersbrook Constructions - SA https://forum.homeone.com.au/viewtopic.php?f=31&t=37762 Current Status: Handover on Thursday!!!!!!!!!!!!!!!!! Re: Our custom build in the Barossa - getting closer 90Feb 15, 2011 10:18 pm https://forum.homeone.com.au/viewtopic.php?f=31&t=43937&start=0 Bought a block in Golden Grove - Jan 2011 Finally finished our design, Mar 2012, *yay* Signed with ADH council consent June 12 Re: Our custom build in the Barossa - getting closer 91Feb 21, 2011 9:08 am ------------------------------------------------------ Handover: 14 December 2010 Current: Putting in plants! My View thread: viewtopic.php?f=31&t=38242&hilit=dechellis+magill Re: Our custom build in the Barossa - getting closer 92Feb 22, 2011 8:48 pm Rebecca Custom Build with Kersbrook Constructions - SA https://forum.homeone.com.au/viewtopic.php?f=31&t=37762 Current Status: Handover on Thursday!!!!!!!!!!!!!!!!! Re: Our custom build in the Barossa - getting closer 93Mar 01, 2011 9:25 pm Rebecca Custom Build with Kersbrook Constructions - SA https://forum.homeone.com.au/viewtopic.php?f=31&t=37762 Current Status: Handover on Thursday!!!!!!!!!!!!!!!!! Re: Our custom build in the Barossa - getting closer 95Mar 03, 2011 3:42 pm Rebecca Custom Build with Kersbrook Constructions - SA https://forum.homeone.com.au/viewtopic.php?f=31&t=37762 Current Status: Handover on Thursday!!!!!!!!!!!!!!!!! Re: Our custom build in the Barossa - getting closer 98Mar 03, 2011 4:07 pm For info on our build: viewtopic.php?f=31&t=43093 Built the McLaren by Dechellis - slab down 22 Feb - handover 30 Aug 2011 - and gardens finished 9 Dec 2012!! Re: Our custom build in the Barossa - getting closer 99Mar 03, 2011 4:37 pm Oh goody - we shall be seeing pics of your build soon then! mrsroc, were you given a reason as to why the insulated walls made it worse? I ask because we are planning to put insulation in the internal walls too. https://forum.homeone.com.au/viewtopic.php?f=31&t=43937&start=0 Bought a block in Golden Grove - Jan 2011 Finally finished our design, Mar 2012, *yay* Signed with ADH council consent June 12 Re: Our custom build in the Barossa - getting closer 100Mar 03, 2011 8:23 pm That really does not make sense to me.....we will have internal insulation on all walls, was never mentioned. It is mainly roof and window sizes along with orientation of you house that will guide the eneregy efficiency calculations. Off to take some pics of some selections and post them! Rebecca Custom Build with Kersbrook Constructions - SA https://forum.homeone.com.au/viewtopic.php?f=31&t=37762 Current Status: Handover on Thursday!!!!!!!!!!!!!!!!! I'd get the gutters to match your roof and pipes to match the paint - otherwise they become a feature. Nice pick with the paint colours! 1 35089 6 57368 Soak wells and electrical run in happening this week! Summit has told me they will relocate the laundry plumbing after the walls are completed. I'm actually pretty happy… 13 36876 |