Browse Forums Building A New House Re: Porter Davis homes 582Nov 23, 2010 9:12 am Initial Deposit 05/09/2010 Tender 21/10/2010 Contract 26/11/2010 Site Start 11 Feb Bricking underway 28/03 Fitout commenced 20/04 PCI 08/07 Settlement 15/07 build Blog http://foxley29.blogspot.com/ Re: Porter Davis homes 586Nov 23, 2010 10:59 am __________________________________________ Built Camberwell 29 with PD - Hand Over was on 22/12/10 http://ssazcamberwell29.blogspot.com/ Re: Porter Davis homes 587Nov 23, 2010 11:02 am OK thanks, I only want downlights in the kitchen/living room, add a few more powerpoints, some external lighting and celing fans in three rooms. Re: Porter Davis homes 588Nov 23, 2010 11:05 am Roshi In the contract it has mentioned that the payment of each stage should be placed in 7 days of receipt of the invoice. But I was able to fix an appointment with the supervisor at the end of this week & it would take more than 7 days to make the payment, if I head to the bank after the inspection. Have anyone face to a similar situation. My CSC informed me better to write to the Accountant.. Any idea whether it would work out... Hi Roshi, I got a building inspector to inspect after frame stage & pre plaster & I didn't pay PD until they rectified the defects stated in the inspection report. I paid my lock up stage 1 month after I received the invoice because I waited for them to fix the defects & I do tell the SS, CSC & Accounts department of what I was doing & they were all right with it. I paid them as soon as they rectified the defects. Please communicate with the account department & tell them that you'll pay the invoice after you've gone through the house with the SS & satisfied that the stage has been completed. Please give her the date of the inspection as well. I find it they are very reasonable if there's still work to be done to complete the stage. __________________________________________ Built Camberwell 29 with PD - Hand Over was on 22/12/10 http://ssazcamberwell29.blogspot.com/ Re: Porter Davis homes 589Nov 23, 2010 11:07 am Audreyand Oscar OK thanks, I only want downlights in the kitchen/living room, add a few more powerpoints, some external lighting and celing fans in three rooms. Ceiling fan will cost you $460 each & downlight I think is $100 each. __________________________________________ Built Camberwell 29 with PD - Hand Over was on 22/12/10 http://ssazcamberwell29.blogspot.com/ Re: Porter Davis homes 590Nov 23, 2010 11:42 am SSAZ Roshi In the contract it has mentioned that the payment of each stage should be placed in 7 days of receipt of the invoice. But I was able to fix an appointment with the supervisor at the end of this week & it would take more than 7 days to make the payment, if I head to the bank after the inspection. Have anyone face to a similar situation. My CSC informed me better to write to the Accountant.. Any idea whether it would work out... Hi Roshi, I got a building inspector to inspect after frame stage & pre plaster & I didn't pay PD until they rectified the defects stated in the inspection report. I paid my lock up stage 1 month after I received the invoice because I waited for them to fix the defects & I do tell the SS, CSC & Accounts department of what I was doing & they were all right with it. I paid them as soon as they rectified the defects. Please communicate with the account department & tell them that you'll pay the invoice after you've gone through the house with the SS & satisfied that the stage has been completed. Please give her the date of the inspection as well. I find it they are very reasonable if there's still work to be done to complete the stage. Hi SSAZ, How much did you pay for your own Inspector & what did that include? (ie. how many visits, was a report supplied, etc, etc). Also, if I may ask where are you building and how did you locate your Inspector, as we're also thinking of hiring an Inspector but are unsure as to how to find someone. Thanks in advance, Chorlton TIMING OF BUILD 25Feb - Site Start 25Mar - Base Stage Complete 31Mar - Frame Completed 11Apr - Roof Tiles 20Apr - Brickwork Started Re: Porter Davis homes 591Nov 23, 2010 11:49 am Chorlton Hello All, For those following our progress, I just wanted to say that we have now signed the Tender Document (Yes we are going to be building with PD) and we have our Tile, Colour & Electrical appointments over the next 2 weeks followed by signing of the Contract a week or so later. Hi Chorlton, You have provided some great advice on the forum, particularly regarding Hopetoun. You have a lot of appointments coming up, could you possibly private message me your name, phone number and lot address so we can simply brief your consultant on your progress so far and ensure the best possible outcome for you on the day? Goodluck with everything and let me know how you go. Cheers, Jess. Porter Davis Homes Questions? Call 1800PORTER Mon - Fri 9am-8pm Sat - Sun 10am-4pm info@porterdavis.com.au http://blog.porterdavis.com.au/ http://www.porterdavishomes.com.au Re: Porter Davis homes 592Nov 23, 2010 11:49 am George's Had 8.5K in mind, and walked out at 13.5K Hi George, If I may ask, (i) what did you ask for that cost $13k !!!!! ??? , and (ii) more specifically, what was the standard number of power points offered throughout your home before any upgrades? So far, I've allowed enough in the budget for around 40 downlights (@ $104 each) and about 13 extra double sockets (@ $50 each). I'm assuming that the standard number of sockets in our homes is about 16. Thanks, Chorlton TIMING OF BUILD 25Feb - Site Start 25Mar - Base Stage Complete 31Mar - Frame Completed 11Apr - Roof Tiles 20Apr - Brickwork Started Re: Porter Davis homes 593Nov 23, 2010 12:16 pm Chorlton Hi SSAZ, How much did you pay for your own Inspector & what did that include? (ie. how many visits, was a report supplied, etc, etc). Also, if I may ask where are you building and how did you locate your Inspector, as we're also thinking of hiring an Inspector but are unsure as to how to find someone. Thanks in advance, Chorlton Hi Chorlton, I'm using New Home Inspections http://www.newhomeinspections.com.au I'm doing 3 inspections, Frame, Pre Plaster & Pre Hand Over. You can find the costs in their website, it depend on whether yours is single or double storeys & they are also giving you discount if you pay within 24 hours. We are building in Blackburn South, Vic. Kevin McDonald, the owner of new home inspections is highly regarded in this homeone forum. I go with them because of recommendation from a cousin & friend. My cousin took her builder all the way to VCAT & Kevin helped her every step of the way. __________________________________________ Built Camberwell 29 with PD - Hand Over was on 22/12/10 http://ssazcamberwell29.blogspot.com/ Re: Porter Davis homes 594Nov 23, 2010 12:18 pm Audreyand Oscar Has anyone had their WIR's fitted (ie not just one standard hnaging rail) through PD - or even know if it is possible? Hi AudreyandOscar, To answer your question, Porter Davis can get our cabinet makers to fitout the entire wardrobe for you, you would just need to get a quote. You can also get these fitted out yourself after handover if you prefer. I hope that helps. Let me know if you have any more questions. Cheers, Jess. Porter Davis Homes Questions? Call 1800PORTER Mon - Fri 9am-8pm Sat - Sun 10am-4pm info@porterdavis.com.au http://blog.porterdavis.com.au/ http://www.porterdavishomes.com.au Re: Porter Davis homes 595Nov 23, 2010 12:20 pm SSAZ Chorlton Hi SSAZ, How much did you pay for your own Inspector & what did that include? (ie. how many visits, was a report supplied, etc, etc). Also, if I may ask where are you building and how did you locate your Inspector, as we're also thinking of hiring an Inspector but are unsure as to how to find someone. Thanks in advance, Chorlton Hi Chorlton, I'm using New Home Inspections http://www.newhomeinspections.com.au I'm doing 3 inspections, Frame, Pre Plaster & Pre Hand Over. You can find the costs in their website, it depend on whether yours is single or double storeys & they are also giving you discount if you pay within 24 hours. We are building in Blackburn South, Vic. Kevin McDonald, the owner of new home inspections is highly regarded in this homeone forum. I go with them because of recommendation from a cousin & friend. My cousin took her builder all the way to VCAT & Kevin helped her every step of the way. Hi SSAZ, Thanks for the prompt & detailed reply. Great Info !! Cheers & All the best...... TIMING OF BUILD 25Feb - Site Start 25Mar - Base Stage Complete 31Mar - Frame Completed 11Apr - Roof Tiles 20Apr - Brickwork Started Re: Porter Davis homes 596Nov 23, 2010 12:24 pm Hi Jess Thanks for that....when you say I just need to get a quote...how would I do that? Re: Porter Davis homes 597Nov 23, 2010 2:06 pm Hi SSAZ, Thanks for the prompt feedback. Yep I will drop an email to the Accounts department specifying that I will make the payment of the frame stage, once I go through the house with the SS. I will not be hiring an independent Inspector at this stage, but will definetly hire at the Lock up & the Pre-handover stages. Hi Chorlton, I am hoping to use the same inspector for the Lock up & the pre handover stages as specified by SSAZ. Kevin at New Home Inspections has been highly recommended by the homeone forum users. If you would like to compare the information & the rates of some other recommended inspectors, please find the following list. Kevin McDonald - New Home Inspections - http://www.newhomeinspections.com.au/ Kris Jones – Blue Square Developments - www.bluesq.com.au Peter – Final Inspect - http://www.finalinspect.com.au/ Darren – Darbecca Pty Ltd - http://qaireporting.com.au/ Mark Whitby - whitbym@optusnet.com.au Additionally, you can find out the inspection companies based on your location by navigating through the following link: http://www.inspectionangel.com.au/vic Good Luck............. Porter Davis - Wembley 35 Contract Signed: 17 Aug 2010 Handover: 12 Aug 2011 Re: Porter Davis homes 598Nov 23, 2010 2:16 pm Hi Roshi, Might want to consider pre plaster, that way the inspector can still check the frame as well. If you do lock up then they can't see the frame & lock up will be duplicated in pre hand over inspection. __________________________________________ Built Camberwell 29 with PD - Hand Over was on 22/12/10 http://ssazcamberwell29.blogspot.com/ Re: Porter Davis homes 599Nov 23, 2010 2:26 pm Roshi Hi SSAZ, Thanks for the prompt feedback. Yep I will drop an email to the Accounts department specifying that I will make the payment of the frame stage, once I go through the house with the SS. I will not be hiring an independent Inspector at this stage, but will definetly hire at the Lock up & the Pre-handover stages. Hi Chorlton, I am hoping to use the same inspector for the Lock up & the pre handover stages as specified by SSAZ. Kevin at New Home Inspections has been highly recommended by the homeone forum users. If you would like to compare the information & the rates of some other recommended inspectors, please find the following list. Kevin McDonald - New Home Inspections - http://www.newhomeinspections.com.au/ Kris Jones – Blue Square Developments - http://www.bluesq.com.au Peter – Final Inspect - http://www.finalinspect.com.au/ Darren – Darbecca Pty Ltd - http://qaireporting.com.au/ Mark Whitby - whitbym@optusnet.com.au Additionally, you can find out the inspection companies based on your location by navigating through the following link: http://www.inspectionangel.com.au/vic Good Luck............. Thanks Roshi..... Appreciate the info TIMING OF BUILD 25Feb - Site Start 25Mar - Base Stage Complete 31Mar - Frame Completed 11Apr - Roof Tiles 20Apr - Brickwork Started Re: Porter Davis homes 600Nov 23, 2010 2:41 pm Hi SSAZ, Many thanks for pointing out the pre-plaster stage inspection. Actually that’s what in my mind, but in the PD Procedure of Purchase there is no stage as such, as it is specified as Lock up after the frame stage. After the frame stage I hope the builder would start the facia, gutter, roof tiling, bricking & the inside work. If I would interest in using an inspector for the pre-plaster stage could you please let me know at which time do I need to hire. Cheers.. Porter Davis - Wembley 35 Contract Signed: 17 Aug 2010 Handover: 12 Aug 2011 Three options 1 Ask the liquidator 2 Find another PD customer and ask the source of their report 3 Pay for new report 3 12345 Ask for references and speak to them. If they are defensive or try to avoid the request, walk. 1 74719 I would never build with Fowler homes. I built with them in 2021 and till date maintenance issues are pending. All their existing trades and businesses don't work with… 14 105617 |