Browse Forums Building A New House 1 Jul 13, 2010 11:42 am contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Carlswil's Statesman Tusmore 4Jul 13, 2010 5:03 pm Contracts signed Dec 09 OK to Start Sep 17 Slab Oct 6 Frame Oct 25,26 Windows and Gutters Oct 28 Bricks Nov 2 -20 Roof Finished Nov 10 Insulation and Gyprock Finished Nov 30 Locked Out Dec 13 Cupboards Installed Dec 17 Tile prep work Dec 26 Painter started Dec 30 Stormwater Jan 17 Tiles Jan 10-19 PCI Feb 2 Handover Feb 9 viewtopic.php?f=31&t=37120[size=85] Re: Carlswil's Statesman Tusmore 6Jul 13, 2010 6:24 pm contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Carlswil's Statesman Tusmore 7Jul 13, 2010 6:28 pm contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Carlswil's Statesman Tusmore 8Jul 13, 2010 6:31 pm contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Carlswil's Statesman Tusmore 10Jul 14, 2010 10:56 am contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Carlswil's Statesman Tusmore - Land settlement done 11Jul 15, 2010 11:06 am contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Carlswil's Statesman Tusmore - Land settlement done 13Jul 15, 2010 11:37 am contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Carlswil's Statesman Tusmore - getting close 15Jul 19, 2010 3:12 pm contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Carlswil's Statesman Tusmore - getting close 17Jul 20, 2010 11:03 pm contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Carlswil's Statesman Tusmore - FHOG extension granted 19Jul 21, 2010 2:15 pm Congratulations! I hope things really start to speed up for you now! I will be watching Contracts signed Dec 09 OK to Start Sep 17 Slab Oct 6 Frame Oct 25,26 Windows and Gutters Oct 28 Bricks Nov 2 -20 Roof Finished Nov 10 Insulation and Gyprock Finished Nov 30 Locked Out Dec 13 Cupboards Installed Dec 17 Tile prep work Dec 26 Painter started Dec 30 Stormwater Jan 17 Tiles Jan 10-19 PCI Feb 2 Handover Feb 9 viewtopic.php?f=31&t=37120[size=85] Re: Carlswil's Statesman Tusmore - FHOG extension granted 20Jul 21, 2010 2:17 pm Thanks Cous and Lucene. I hope things speed up too. As soon as there is some movement at my block, I will take pics and put them up. Now that will be exciting (well for me anyway) contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 there should be ss cable so you can pull up bore pump for service 1 3437 Hi all, Need some ideas for my front yard. There are a few elements where the landscaping needs to take into account: There is a slight slope forward with steps going to… 0 3502 can someone with more experience give me their insight? land is pretty much flat its pretty much at the top of a hill. left and right neighbours are flat in line with my… 0 7607 |