Browse Forums Building A New House 1 Jul 15, 2010 11:50 am Site Start: 10th September, 2010 PCI : Friday 27th January, 2011. Handover: 3rd February, 2011 Build Thread: viewtopic.php?f=31&t=37677 Re: Copy of Bank Docs to Builder 2Jul 15, 2010 12:04 pm Land Settled: 29 March 2010 Pre contract & Deposit paid - 17 May 2010 Pre Start & Contracts Signed - 16 June 2010 Council Approval Received - 30 June 2010 Slab Down 30 July 2010 Plate High - Late August Lock Up - TBA Re: Copy of Bank Docs to Builder 3Jul 15, 2010 12:18 pm contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Copy of Bank Docs to Builder 4Jul 15, 2010 12:30 pm Site Start: 10th September, 2010 PCI : Friday 27th January, 2011. Handover: 3rd February, 2011 Build Thread: viewtopic.php?f=31&t=37677 Re: Copy of Bank Docs to Builder 6Jul 15, 2010 12:49 pm Site Start: 10th September, 2010 PCI : Friday 27th January, 2011. Handover: 3rd February, 2011 Build Thread: viewtopic.php?f=31&t=37677 Re: Copy of Bank Docs to Builder 9Jul 16, 2010 10:51 am Land Settled: 29 March 2010 Pre contract & Deposit paid - 17 May 2010 Pre Start & Contracts Signed - 16 June 2010 Council Approval Received - 30 June 2010 Slab Down 30 July 2010 Plate High - Late August Lock Up - TBA Re: Copy of Bank Docs to Builder 15Jul 17, 2010 5:46 pm We are with one of the big four banks, didn't go through a broker, and also needed to provide our signed documents to our builder. We also needed a letter from our conveyer that proved settlement on our land, before they would step foot onsite. We are building with a small family builder. Just protecting themselves really. Dear J.K. Rowling, Your books are entirely unrealistic. I mean, a ginger kid with two friends? Sincerely, Anonymous How much are you ahead in payments compared to where the build is at? Have you fully drawn down the loan? 5 12043 Hi Mofflepop, I would recommend finding a building designer to prepare plans, they should design to your specified budget. The benefit is you can tender the project out… 9 20679 |