Browse Forums Building A New House Re: Building with Gemmill Homes - The Nevada 22Jun 24, 2010 3:13 pm Building The Nevada with Gemmill Homes Slab down 16/8/10 Bricks delivered 7/9/10 Brickies started 9/9/10 Roof completed 27/10/10 Lock up 1/12/10 My thread: https://forum.homeone.com.au/viewtopic.php?f=31&t=36483&p=537529#p537529 Re: Building with Gemmill Homes - The Nevada 23Jun 25, 2010 12:34 am Building with Gemmill Homes - The Nevada Contract sign: early September 2009 Job Start: 12 January 2010 Slab down: mid February 2010 Brickwork fin: end April 2010 Roofing fin: end June 2010 Lock up: mid July 2010 Cabinets and shelving fin: end of July 2010 Practical Completion Meeting: 28 September 2010 My thread: viewtopic.php?f=31&t=28341 Re: Building with Gemmill Homes - The Nevada 26Jun 26, 2010 1:38 pm Building The Nevada with Gemmill Homes Slab down 16/8/10 Bricks delivered 7/9/10 Brickies started 9/9/10 Roof completed 27/10/10 Lock up 1/12/10 My thread: https://forum.homeone.com.au/viewtopic.php?f=31&t=36483&p=537529#p537529 Re: Building with Gemmill Homes - The Nevada 27Jun 26, 2010 10:38 pm Building the Nevada by Gemmill Homes in Seville Grove Contract signed 17/07/10 Pre-Start 09/08/10 Earthwords 01/10/10 Slab down 13/10/10 Brickies Start 4/11/10 Bricks finished 7/12/10 https://forum.homeone.com.au/viewtopic.php?f=31&t=37039 Re: Building with Gemmill Homes - The Nevada 28Jun 27, 2010 9:52 pm Building with Gemmill Homes - The Nevada Contract sign: early September 2009 Job Start: 12 January 2010 Slab down: mid February 2010 Brickwork fin: end April 2010 Roofing fin: end June 2010 Lock up: mid July 2010 Cabinets and shelving fin: end of July 2010 Practical Completion Meeting: 28 September 2010 My thread: viewtopic.php?f=31&t=28341 Re: Building with Gemmill Homes - The Nevada 30Jun 29, 2010 2:08 am Building with Gemmill Homes - The Nevada Contract sign: early September 2009 Job Start: 12 January 2010 Slab down: mid February 2010 Brickwork fin: end April 2010 Roofing fin: end June 2010 Lock up: mid July 2010 Cabinets and shelving fin: end of July 2010 Practical Completion Meeting: 28 September 2010 My thread: viewtopic.php?f=31&t=28341 Re: Building with Gemmill Homes - The Nevada 31Jun 29, 2010 9:38 pm Building with Gemmill Homes - The Nevada Contract sign: early September 2009 Job Start: 12 January 2010 Slab down: mid February 2010 Brickwork fin: end April 2010 Roofing fin: end June 2010 Lock up: mid July 2010 Cabinets and shelving fin: end of July 2010 Practical Completion Meeting: 28 September 2010 My thread: viewtopic.php?f=31&t=28341 Re: Building with Gemmill Homes - The Nevada 32Jun 30, 2010 11:50 am Building The Nevada with Gemmill Homes Slab down 16/8/10 Bricks delivered 7/9/10 Brickies started 9/9/10 Roof completed 27/10/10 Lock up 1/12/10 My thread: https://forum.homeone.com.au/viewtopic.php?f=31&t=36483&p=537529#p537529 Re: Building with Gemmill Homes - The Nevada 34Jun 30, 2010 9:16 pm *Built with Gemmill Homes in WA* Slab - 1st June 2009 Plate Height - 17th June 2009 Lock Up - 18th August 2009 PCI - 5th October 2009 Hand Over - 15th Oct 2009 https://forum.homeone.com.au/viewtopic.php?f=31&t=20844 Re: Building with Gemmill Homes - The Nevada 35Jul 13, 2010 2:50 pm Building in Cockburn, WA, with Dale Alcock https://forum.homeone.com.au/viewtopic.php?f=31&t=29597 Siteworks 9 February 2010 Slab 15 February 2010 Bricks commenced 6 March 2010 Roof commenced 30 March 2010 BIR Submitted 14 May 2010 Lockup 27 May 2010 PCI 22 September 2010 Keys 8 October 2010 Roof finally finished 13 Oct Moved in 30 October 2010 Re: Building with Gemmill Homes - The Nevada 36Jul 13, 2010 5:29 pm Building The Nevada with Gemmill Homes Slab down 16/8/10 Bricks delivered 7/9/10 Brickies started 9/9/10 Roof completed 27/10/10 Lock up 1/12/10 My thread: https://forum.homeone.com.au/viewtopic.php?f=31&t=36483&p=537529#p537529 Re: Building with Gemmill Homes - The Nevada 37Jul 15, 2010 1:26 am Building with Gemmill Homes - The Nevada Contract sign: early September 2009 Job Start: 12 January 2010 Slab down: mid February 2010 Brickwork fin: end April 2010 Roofing fin: end June 2010 Lock up: mid July 2010 Cabinets and shelving fin: end of July 2010 Practical Completion Meeting: 28 September 2010 My thread: viewtopic.php?f=31&t=28341 Re: Building with Gemmill Homes - The Nevada 38Jul 15, 2010 1:38 am Building with Gemmill Homes - The Nevada Contract sign: early September 2009 Job Start: 12 January 2010 Slab down: mid February 2010 Brickwork fin: end April 2010 Roofing fin: end June 2010 Lock up: mid July 2010 Cabinets and shelving fin: end of July 2010 Practical Completion Meeting: 28 September 2010 My thread: viewtopic.php?f=31&t=28341 Re: Building with Gemmill Homes - The Nevada 39Jul 15, 2010 1:22 pm Hi henfry We had the same roof tiles put on our house last week and are just as disappointed as you. Not happy with the chips and the uneverness of the way the tiles were laid. After the rain on the weekend the front part of our house was flooded again so its definetly not water tight!. We actually drove past your place and thought that your tiles looked slightly better than ours! We had a building inspector come out and look at our place on tuesday and he did confirm that the roof is done in two stages and they send someone back from bristile to change cracked tiles, fix up ridge capping and paint any of the surface chips. The painters also come in and paint the ridge capping and cuts to make them the same colour as the roof. It probably doesn't make you feel any better than our building inspector told us that these tiles are actually one of the worst on the market for chipping and uniformity. And the darker the colour the worst they are! I wish someone had told us this before we picked them. Im pretty sure that the tiles will get fixed and hopefully when the houses are finished they will look so much better. Congrats on getting your ceilings and plastering done. We are still waiting on our place to dryout before the render will start, hopefully later this week or early next week. Good luck with the rest our your build i hope it goes more smoothly. I would never build with Fowler homes. I built with them in 2021 and till date maintenance issues are pending. All their existing trades and businesses don't work with… 14 109506 Hi there! Putting the feelers out there for those who have (or almost) built with Arli homes! Interested in your experiences who've built from their stock home designs… 0 26589 Wish you all the best. Once you signed the contract, they will find millions excuses to charge you. And have seen their sites unfinished for a long time. 4 25783 |